Question 150
A team must implement a control for the following situation: A retailer promises to address six urgent risks but sets no owners or acceptance checkpoints. Which design detail fits best?
Explanation
Correct Answer
Define tasks, prerequisites, resourcing, milestones, residual-risk reassessment and owner approval. This design addresses the issue that a retailer promises to address six urgent risks but sets no owners or acceptance checkpoints. It implements the decision to plan control implementation with accountable ownership, resources, timing and verification. Verify that progress records show completion and tested effectiveness against the treatment plan. A failure would be treating a risk register entry as an actionable deployment plan without owners or dates.
Incorrect Answers
Use evidence about threat exposure, controls and information impact to justify risk ratings. That approach concerns likelihood and consequence appraisal, as when a regional retailer calls a rare database outage catastrophic without estimating how likely it is. This case instead requires the team to define tasks, prerequisites, resourcing, milestones, residual-risk reassessment and owner approval. The remaining risk is unfulfilled treatment commitments and uncontrolled late delivery. Case: A retailer promises to address six urgent risks but sets no owners or acceptance checkpoints.
Record operating model, technology, legal environment, competition and change drivers with periodic review. That approach concerns context and external factors, as when a retailer expands into another jurisdiction but its security plan ignores new contractual and statutory constraints. This case instead requires the team to define tasks, prerequisites, resourcing, milestones, residual-risk reassessment and owner approval. The remaining risk is unfulfilled treatment commitments and uncontrolled late delivery. Case: A retailer promises to address six urgent risks but sets no owners or acceptance checkpoints.
Specify assets, scenarios, likelihood, impact, risk criteria and repeatability rules. That approach concerns risk assessment methodology selection, as when a bank treats every identified threat as unacceptable because impact criteria were never defined. This case instead requires the team to define tasks, prerequisites, resourcing, milestones, residual-risk reassessment and owner approval. The remaining risk is unfulfilled treatment commitments and uncontrolled late delivery. Case: A retailer promises to address six urgent risks but sets no owners or acceptance checkpoints.