Question 280
A program is built around technology products without stating which business risks it serves. Which management response BEST addresses the stated risk or governance priority?
Explanation
Correct Answer
Risk alignment keeps program scope tied to enterprise value rather than tools. This directly meets the requirement to connect the security program to enterprise exposure.
Incorrect Answers
Program execution depends on functions that security management does not directly command. That action would coordinate program-wide stakeholder responsibilities; it does not address the case's priority to connect the security program to enterprise exposure.
Program delivery is complete when durable operating responsibility is established. It is primarily relevant when the need is to establish program delivery exit criteria, rather than to connect the security program to enterprise exposure.
A charter translates enterprise strategy into governed capabilities and accountability. This would help define an integrated information security program; the scenario instead requires a decision to connect the security program to enterprise exposure.