Pass Your Isaca CISA Exam Easy!

Isaca CISA Exam Questions & Answers, Accurate & Verified By IT Experts

Instant Download, Free Fast Updates, 99.6% Pass Rate

CISA Premium Bundle

$79.99

Isaca CISA Premium Bundle

CISA Premium File: 1097 Questions & Answers

Last Update: Oct 27, 2026

CISA Training Course: 74 Video Lectures

CISA PDF Study Guide: 1141 Pages

CISA Bundle gives you unlimited access to "CISA" files. However, this does not replace the need for a .vce exam simulator. To download VCE exam simulator click here
Isaca CISA Premium Bundle
Isaca CISA Premium Bundle

CISA Premium File: 1097 Questions & Answers

Last Update: Oct 27, 2026

CISA Training Course: 74 Video Lectures

CISA PDF Study Guide: 1141 Pages

$79.99

CISA Bundle gives you unlimited access to "CISA" files. However, this does not replace the need for a .vce exam simulator. To download your .vce exam simulator click here

Isaca CISA Practice Test 34

Question 330

The audit team proposes this response: Assess whether program reporting includes risk, dependencies, benefits and realistic delivery status. For the situation—A program dashboard shows green milestones though the project risk register omits a critical supplier dependency. Which evidence would BEST demonstrate that the response was effective?

  1. Reconcile management summaries with defect, dependency, budget and risk records.
  2. Inspect defect severity, owner decisions, workarounds and readiness checklist.
  3. Attempt authorized and unauthorized configuration changes and recompute selected transactions.
  4. Compare post-go-live incident metrics and peak-load behavior against acceptance thresholds.

Explanation

Correct Answer

A:

Effective project governance requires transparent indicators beyond schedule color codes. The auditor should retain enough source context to reproduce the conclusion.

Incorrect Answers

B:

The auditor should retain enough source context to reproduce the conclusion. The appropriate remedy is to reconcile management summaries with defect, dependency, budget and risk records.

C:

Application control design must protect the integrity of both inputs and business rules. Instead, the response must reconcile management summaries with defect, dependency, budget and risk records.

D:

The auditor should retain enough source context to reproduce the conclusion. The relevant control is to reconcile management summaries with defect, dependency, budget and risk records.

Question 331

At a second company, executive reporting focuses on spend and dates but not unresolved quality and security risks. Which assurance principle BEST explains the audit implication?

  1. Effective project governance requires transparent indicators beyond schedule color codes.
  2. Implementation success should be reassessed using real operating conditions and feedback.
  3. Business-case choices require assessment of uncertainty and risk, not only one-point forecasts.
  4. A sound business case measures achievable outcomes and full lifecycle cost rather than features alone.

Explanation

Correct Answer

A:

This principle explains the control or assurance implication in the second, independent scenario. Effective project governance requires transparent indicators beyond schedule color codes. The auditor should relate that principle to the observed evidence.

Incorrect Answers

B:

This is a valid consideration in post-implementation review; the scenario instead turns on a different, more specific assurance requirement.

C:

This is a valid consideration in business case and feasibility analysis; the scenario instead turns on a different, more specific assurance requirement.

D:

This is a valid consideration in business case and feasibility analysis; the scenario instead turns on a different, more specific assurance requirement.

Question 332

At a second company, executive reporting focuses on spend and dates but not unresolved quality and security risks. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?

  1. An update ticket without exact configuration differences is insufficient reconstruction evidence.
  2. Meeting a deployment deadline does not by itself establish benefit realization.
  3. Closing the project financially does not automatically close its unresolved security issues.
  4. A green project status is not proof that major delivery risks are controlled.

Explanation

Correct Answer

D:

A green project status is not proof that major delivery risks are controlled. The underlying issue is that effective project governance requires transparent indicators beyond schedule color codes.

Incorrect Answers

A:

That caution could matter when assessing implementation configuration and release management, but it is not the most immediate unsupported assumption in this case.

B:

That caution could matter when assessing post-implementation review, but it is not the most immediate unsupported assumption in this case.

C:

That caution could matter when assessing post-implementation review, but it is not the most immediate unsupported assumption in this case.

Question 333

A steering committee approves a major design change without knowing its cost or impact on existing controls. Which response should an IS auditor recommend as MOST appropriate?

  1. Test recovery and rollback using realistic service scenarios prior to production cutover.
  2. Require formal impact assessment and change authorization before modifying key project baselines.
  3. Identify fraud and error risks and design preventive segregation or approved compensating controls.
  4. Assess secure software development, review, build integrity and environment segregation.

Explanation

Correct Answer

B:

Controlled project change management protects objectives and assurance scope from unexamined drift. The most directly responsive audit action is: Require formal impact assessment and change authorization before modifying key project baselines. Verification should include: Inspect change records for cost, dependency, security, testing and stakeholder approvals.

Incorrect Answers

A:

Operational readiness includes demonstrated recovery capability, not only a written procedure. The needed step here is to require formal impact assessment and change authorization before modifying key project baselines.

C:

Control design must address the relevant risk path, not rely on an unrelated security feature. The appropriate remedy is to require formal impact assessment and change authorization before modifying key project baselines.

D:

Secure development requires traceability of changes and trusted software artifacts throughout delivery. Instead, the response must require formal impact assessment and change authorization before modifying key project baselines.

Question 334

The audit team proposes this response: Require formal impact assessment and change authorization before modifying key project baselines. For the situation—A steering committee approves a major design change without knowing its cost or impact on existing controls. Which evidence would BEST demonstrate that the response was effective?

  1. Review timed exercises, data integrity checks and return-to-service evidence.
  2. Inspect change records for cost, dependency, security, testing and stakeholder approvals.
  3. Compare baseline and actual service measures, user outcomes and issue closure against commitments.
  4. Check in-flight queue counts, sequence identifiers and business confirmation after cutover.

Explanation

Correct Answer

B:

Controlled project change management protects objectives and assurance scope from unexamined drift. The auditor should retain enough source context to reproduce the conclusion.

Incorrect Answers

A:

The auditor should retain enough source context to reproduce the conclusion. The relevant control is to inspect change records for cost, dependency, security, testing and stakeholder approvals.

C:

The auditor should retain enough source context to reproduce the conclusion. The needed step here is to inspect change records for cost, dependency, security, testing and stakeholder approvals.

D:

Migration control must account for transactions occurring between old and new states. The appropriate remedy is to inspect change records for cost, dependency, security, testing and stakeholder approvals.

Question 335

At another entity, a project changes integration patterns after testing began but does not update the acceptance baseline. Which assurance principle BEST explains the audit implication?

  1. Controlled project change management protects objectives and assurance scope from unexamined drift.
  2. Agile delivery can support strong controls when assurance activities are integrated into each iteration.
  3. Deployment approval should reflect actual residual risk against pre-agreed go-live criteria.
  4. Segregation in release management limits unauthorized or unreviewed production changes.

Explanation

Correct Answer

A:

This principle explains the control or assurance implication in the second, independent scenario. Controlled project change management protects objectives and assurance scope from unexamined drift. The auditor should relate that principle to the observed evidence.

Incorrect Answers

B:

This is a valid consideration in system development methodologies; the scenario instead turns on a different, more specific assurance requirement.

C:

This is a valid consideration in system readiness and implementation testing; the scenario instead turns on a different, more specific assurance requirement.

D:

This is a valid consideration in implementation configuration and release management; the scenario instead turns on a different, more specific assurance requirement.

Question 336

At another entity, a project changes integration patterns after testing began but does not update the acceptance baseline. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?

  1. A technically feasible enhancement is not automatically an approved change to business commitments.
  2. An early signed-off specification is not always current after legitimate business changes.
  3. An optimistic payback number is not an objective guarantee of value.
  4. Passing application tests does not validate a package that differs from the reviewed build.

Explanation

Correct Answer

A:

A technically feasible enhancement is not automatically an approved change to business commitments. The underlying issue is that controlled project change management protects objectives and assurance scope from unexamined drift.

Incorrect Answers

B:

That caution could matter when assessing system development methodologies, but it is not the most immediate unsupported assumption in this case.

C:

That caution could matter when assessing business case and feasibility analysis, but it is not the most immediate unsupported assumption in this case.

D:

That caution could matter when assessing system development methodologies, but it is not the most immediate unsupported assumption in this case.

Question 337

A large implementation has no defined independent quality or security oversight role. Which response should an IS auditor recommend as MOST appropriate?

  1. Maintain approved configuration baselines and reproducible release change records.
  2. Recommend independent program assurance and escalation for material delivery control deficiencies.
  3. Define validated rollback, retention and cutover decision criteria before retiring legacy services.
  4. Plan transaction cutover, interface quiescence or controlled replay and end-to-end reconciliation.

Explanation

Correct Answer

B:

Independent project assurance improves objectivity over high-impact delivery risks. The most directly responsive audit action is: Recommend independent program assurance and escalation for material delivery control deficiencies. Verification should include: Inspect governance charters, oversight reports and evidence of issue closure review.

Incorrect Answers

A:

Baseline configuration management supports traceability, change impact and reliable recovery. The acceptance criterion here is: Recommend independent program assurance and escalation for material delivery control deficiencies.

C:

Migration risk requires a feasible recovery path until converted services are accepted. What must be demonstrated is: Recommend independent program assurance and escalation for material delivery control deficiencies.

D:

Migration control must account for transactions occurring between old and new states. The appropriate comparison is: Recommend independent program assurance and escalation for material delivery control deficiencies.

Question 338

The audit team proposes this response: Recommend independent program assurance and escalation for material delivery control deficiencies. For the situation—A large implementation has no defined independent quality or security oversight role. Which evidence would BEST demonstrate that the response was effective?

  1. Recalculate total cost of ownership using documented volumes, exit costs and support requirements.
  2. Verify approved commits, build artifact hashes, automated gate results and deployment authorization.
  3. Attempt authorized and unauthorized configuration changes and recompute selected transactions.
  4. Inspect governance charters, oversight reports and evidence of issue closure review.

Explanation

Correct Answer

D:

Independent project assurance improves objectivity over high-impact delivery risks. The auditor should retain enough source context to reproduce the conclusion.

Incorrect Answers

A:

Financial feasibility depends on realistic complete costs and measurable benefit timing. Instead, the response must inspect governance charters, oversight reports and evidence of issue closure review.

B:

Secure development requires traceability of changes and trusted software artifacts throughout delivery. The relevant control is to inspect governance charters, oversight reports and evidence of issue closure review.

C:

Application control design must protect the integrity of both inputs and business rules. The needed step here is to inspect governance charters, oversight reports and evidence of issue closure review.

Question 339

In a second program, delivery teams close their own high-severity audit issues without challenge. Which assurance principle BEST explains the audit implication?

  1. Using external developers does not transfer accountability for enterprise requirements and assurance.
  2. Migration risk requires a feasible recovery path until converted services are accepted.
  3. Data migration assurance must address completeness and accuracy, not just successful file transfer.
  4. Independent project assurance improves objectivity over high-impact delivery risks.

Explanation

Correct Answer

D:

This principle explains the control or assurance implication in the second, independent scenario. Independent project assurance improves objectivity over high-impact delivery risks. The auditor should relate that principle to the observed evidence.

Incorrect Answers

A:

This is a valid consideration in system development methodologies; the scenario instead turns on a different, more specific assurance requirement.

B:

This is a valid consideration in system migration, infrastructure deployment, and data conversion; the scenario instead turns on a different, more specific assurance requirement.

C:

This is a valid consideration in system migration, infrastructure deployment, and data conversion; the scenario instead turns on a different, more specific assurance requirement.

Question 340

In a second program, delivery teams close their own high-severity audit issues without challenge. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?

  1. Project-team self-certification cannot always replace independent program-level oversight.
  2. Matching the number of copied files cannot prove that converted business values are correct.
  3. Technical feasibility alone does not demonstrate an implementable compliant business solution.
  4. Closing the project financially does not automatically close its unresolved security issues.

Explanation

Correct Answer

A:

Project-team self-certification cannot always replace independent program-level oversight. The underlying issue is that independent project assurance improves objectivity over high-impact delivery risks.

Incorrect Answers

B:

That caution could matter when assessing system migration, infrastructure deployment, and data conversion, but it is not the most immediate unsupported assumption in this case.

C:

That caution could matter when assessing business case and feasibility analysis, but it is not the most immediate unsupported assumption in this case.

D:

That caution could matter when assessing post-implementation review, but it is not the most immediate unsupported assumption in this case.


Certified Information Systems Auditor (CISA) Practice Tests

Purchase Individually

CISA Premium File

Premium File
CISA Premium File
1097 Q&A
$76.99$69.99

CISA Training Video Course

Training Course
CISA Training Video Course
74 Lectures
$27.49$24.99

CISA Study Guide

Study Guide
CISA Study Guide
1141 PDF Pages
$27.49$24.99

Site Search:

 

VISA, MasterCard, AmericanExpress, UnionPay

SPECIAL OFFER: GET 10% OFF

ExamCollection Premium

ExamCollection Premium Files

Pass your Exam with ExamCollection's PREMIUM files!

  • ExamCollection Certified Safe Files
  • Guaranteed to have ACTUAL Exam Questions
  • Up-to-Date Exam Study Material - Verified by Experts
  • Instant Downloads
Enter Your Email Address to Receive Your 10% Off Discount Code
A Confirmation Link will be sent to this email address to verify your login
We value your privacy. We will not rent or sell your email address

SPECIAL OFFER: GET 10% OFF

Use Discount Code:

MIN10OFF

A confirmation link was sent to your e-mail.
Please check your mailbox for a message from support@examcollection.com and follow the directions.

Next

Download Free Demo of VCE Exam Simulator

Experience Avanset VCE Exam Simulator for yourself.

Simply submit your e-mail address below to get started with our interactive software demo of your free trial.

Free Demo Limits: In the demo version you will be able to access only first 5 questions from exam.