Pass Your Isaca CISA Exam Easy!

Isaca CISA Exam Questions & Answers, Accurate & Verified By IT Experts

Instant Download, Free Fast Updates, 99.6% Pass Rate

CISA Premium Bundle

$79.99

Isaca CISA Premium Bundle

CISA Premium File: 1097 Questions & Answers

Last Update: Oct 27, 2026

CISA Training Course: 74 Video Lectures

CISA PDF Study Guide: 1141 Pages

CISA Bundle gives you unlimited access to "CISA" files. However, this does not replace the need for a .vce exam simulator. To download VCE exam simulator click here
Isaca CISA Premium Bundle
Isaca CISA Premium Bundle

CISA Premium File: 1097 Questions & Answers

Last Update: Oct 27, 2026

CISA Training Course: 74 Video Lectures

CISA PDF Study Guide: 1141 Pages

$79.99

CISA Bundle gives you unlimited access to "CISA" files. However, this does not replace the need for a .vce exam simulator. To download your .vce exam simulator click here

Isaca CISA Practice Test 19

Question 180

The audit team proposes this response: Assess whether IT governance decisions and investments align with approved enterprise strategy. For the situation—An enterprise IT steering committee approves technology purchases without reference to strategic business priorities. Which evidence would BEST demonstrate that the response was effective?

  1. Compare demand projections and operational staffing plans against actual growth and service indicators.
  2. Trace prioritized initiatives through business objectives, decision authority, benefits and performance measures.
  3. Compare data flows, notices, consent or other legal basis and privacy impact assessments.
  4. Verify subcontractor inventory, concentration risk, service continuity evidence and exit provisions.

Explanation

Correct Answer

B:

Effective IT governance aligns technology strategy with enterprise goals and accountability. The auditor should retain enough source context to reproduce the conclusion.

Incorrect Answers

A:

Resource allocation should reflect business demand and service capability rather than historical spending alone. The needed step here is to trace prioritized initiatives through business objectives, decision authority, benefits and performance measures.

C:

Privacy purpose limitation and transparency should govern subsequent use of personal data. The appropriate remedy is to trace prioritized initiatives through business objectives, decision authority, benefits and performance measures.

D:

This observation could inform an assessment of it vendor management, but it would not directly demonstrate the corrective action in the present case.

Question 181

At a retailer, the IT roadmap grows rapidly but there is no traceability to business outcomes or oversight decisions. Which assurance principle BEST explains the audit implication?

  1. Effective IT governance aligns technology strategy with enterprise goals and accountability.
  2. Policies state organizational intent while standards and procedures make execution repeatable and measurable.
  3. Data governance aligns ownership, classification and authorized use throughout information flows.
  4. Privacy purpose limitation and transparency should govern subsequent use of personal data.

Explanation

Correct Answer

A:

This principle explains the control or assurance implication in the second, independent scenario. Effective IT governance aligns technology strategy with enterprise goals and accountability. The auditor should relate that principle to the observed evidence.

Incorrect Answers

B:

This is a valid consideration in it policies, standards, procedures and practices; the scenario instead turns on a different, more specific assurance requirement.

C:

This is a valid consideration in data governance and classification; the scenario instead turns on a different, more specific assurance requirement.

D:

This is a valid consideration in privacy program and principles; the scenario instead turns on a different, more specific assurance requirement.

Question 182

At a retailer, the IT roadmap grows rapidly but there is no traceability to business outcomes or oversight decisions. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?

  1. Outsourcing a control does not remove the enterprise's duty to oversee residual risk.
  2. Technical sophistication alone does not demonstrate strategic IT value.
  3. A flat budget does not prove that capacity will remain sufficient under changing demand.
  4. Developer confidence alone cannot replace appropriate independent acceptance evidence.

Explanation

Correct Answer

B:

Technical sophistication alone does not demonstrate strategic IT value. The underlying issue is that effective IT governance aligns technology strategy with enterprise goals and accountability.

Incorrect Answers

A:

That caution could matter when assessing enterprise risk management, but it is not the most immediate unsupported assumption in this case.

C:

That caution could matter when assessing it resource management, but it is not the most immediate unsupported assumption in this case.

D:

That caution could matter when assessing quality assurance and quality management of it, but it is not the most immediate unsupported assumption in this case.

Question 183

The CIO controls IT budget, risk acceptance and internal audit conclusions without independent oversight. Which response should an IS auditor recommend as MOST appropriate?

  1. Evaluate segregation of governance, management and assurance responsibilities with independent escalation.
  2. Evaluate vendor obligations against enterprise legal, security and service needs, not uptime alone.
  3. Map material fourth-party dependencies and assess provider oversight of the subcontractor chain.
  4. Assess exit, transition, data portability and recovery clauses before relying on the outsourced service.

Explanation

Correct Answer

A:

Governance oversight must remain distinguishable from operational management and independent assurance. The most directly responsive audit action is: Evaluate segregation of governance, management and assurance responsibilities with independent escalation. Verification should include: Inspect charters, approval matrices and board committee minutes for oversight and conflict safeguards.

Incorrect Answers

B:

Vendor governance must monitor all material risk and contractual performance dimensions. Instead, the response must evaluate segregation of governance, management and assurance responsibilities with independent escalation.

C:

Supplier risk extends beyond immediate vendors to material downstream dependencies. The relevant control is to evaluate segregation of governance, management and assurance responsibilities with independent escalation.

D:

Supplier management includes continuity and secure termination, not only selection and renewal. The needed step here is to evaluate segregation of governance, management and assurance responsibilities with independent escalation.

Question 184

The audit team proposes this response: Evaluate segregation of governance, management and assurance responsibilities with independent escalation. For the situation—The CIO controls IT budget, risk acceptance and internal audit conclusions without independent oversight. Which evidence would BEST demonstrate that the response was effective?

  1. Inspect contractual obligations, actual incident notices and escalation exercises.
  2. Inspect dependency diagrams, interface contracts and end-to-end integration test results.
  3. Verify exception approval and a migration or remediation roadmap for nonconforming deployments.
  4. Inspect charters, approval matrices and board committee minutes for oversight and conflict safeguards.

Explanation

Correct Answer

D:

Governance oversight must remain distinguishable from operational management and independent assurance. The auditor should retain enough source context to reproduce the conclusion.

Incorrect Answers

A:

Vendor governance must monitor all material risk and contractual performance dimensions. The appropriate remedy is to inspect charters, approval matrices and board committee minutes for oversight and conflict safeguards.

B:

The auditor should retain enough source context to reproduce the conclusion. Instead, the response must inspect charters, approval matrices and board committee minutes for oversight and conflict safeguards.

C:

The auditor should retain enough source context to reproduce the conclusion. The relevant control is to inspect charters, approval matrices and board committee minutes for oversight and conflict safeguards.

Question 185

At another company, a senior technology executive can unilaterally waive control findings and close audit issues. Which assurance principle BEST explains the audit implication?

  1. Privacy governance extends to external processors and international data handling.
  2. Governance oversight must remain distinguishable from operational management and independent assurance.
  3. Resource management includes continuity of expertise needed to deliver IT services.
  4. Operational KPIs should reflect actual service quality, and KRIs should reveal emerging exposure.

Explanation

Correct Answer

B:

This principle explains the control or assurance implication in the second, independent scenario. Governance oversight must remain distinguishable from operational management and independent assurance. The auditor should relate that principle to the observed evidence.

Incorrect Answers

A:

This is a valid consideration in privacy program and principles; the scenario instead turns on a different, more specific assurance requirement.

C:

This is a valid consideration in it resource management; the scenario instead turns on a different, more specific assurance requirement.

D:

This is a valid consideration in it performance monitoring and reporting; the scenario instead turns on a different, more specific assurance requirement.

Question 186

At another company, a senior technology executive can unilaterally waive control findings and close audit issues. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?

  1. Identical labels in two systems do not guarantee the same business meaning.
  2. Completing a project plan item is not the same as improving actual service quality.
  3. One executive's approval cannot replace independent oversight of that executive's decisions.
  4. Labeling work urgent does not justify eliminating every control and record.

Explanation

Correct Answer

C:

One executive's approval cannot replace independent oversight of that executive's decisions. The underlying issue is that governance oversight must remain distinguishable from operational management and independent assurance.

Incorrect Answers

A:

That caution could matter when assessing enterprise architecture and considerations, but it is not the most immediate unsupported assumption in this case.

B:

That caution could matter when assessing quality assurance and quality management of it, but it is not the most immediate unsupported assumption in this case.

D:

That caution could matter when assessing it policies, standards, procedures and practices, but it is not the most immediate unsupported assumption in this case.

Question 187

A cloud initiative changes from on-premises hosting to SaaS but governance committees retain obsolete decision rights. Which response should an IS auditor recommend as MOST appropriate?

  1. Review treatment options, contractual limits and retained business risk ownership before accepting the plan.
  2. Evaluate vendor obligations against enterprise legal, security and service needs, not uptime alone.
  3. Clarify governance authority, accountability and escalation after organizational or technology change.
  4. Compare implemented solutions with approved architectural principles and formally governed deviations.

Explanation

Correct Answer

C:

Governance structures must fit the current organization, decision scope and risk ownership. The most directly responsive audit action is: Clarify governance authority, accountability and escalation after organizational or technology change. Verification should include: Review updated RACI, policy authority and evidence of consistent decisions in affected initiatives.

Incorrect Answers

A:

Transferring a service or funding a treatment does not necessarily transfer all enterprise consequences. The appropriate comparison is: Clarify governance authority, accountability and escalation after organizational or technology change.

B:

Vendor governance must monitor all material risk and contractual performance dimensions. The relevant evidence instead is: Clarify governance authority, accountability and escalation after organizational or technology change.

D:

Architecture governance evaluates conformance between target state and actual technology decisions. The acceptance criterion here is: Clarify governance authority, accountability and escalation after organizational or technology change.

Question 188

The audit team proposes this response: Clarify governance authority, accountability and escalation after organizational or technology change. For the situation—A cloud initiative changes from on-premises hosting to SaaS but governance committees retain obsolete decision rights. Which evidence would BEST demonstrate that the response was effective?

  1. Review updated RACI, policy authority and evidence of consistent decisions in affected initiatives.
  2. Trace samples from source classification through downstream exports and access control.
  3. Verify the data inventory, lawful basis, notices and approved purpose mapping for the relevant population.
  4. Inspect tested exit plans, escrow where appropriate and contract rights over data return.

Explanation

Correct Answer

A:

Governance structures must fit the current organization, decision scope and risk ownership. The auditor should retain enough source context to reproduce the conclusion.

Incorrect Answers

B:

The auditor should retain enough source context to reproduce the conclusion. The needed step here is to review updated RACI, policy authority and evidence of consistent decisions in affected initiatives.

C:

The auditor should retain enough source context to reproduce the conclusion. The appropriate remedy is to review updated RACI, policy authority and evidence of consistent decisions in affected initiatives.

D:

Supplier management includes continuity and secure termination, not only selection and renewal. Instead, the response must review updated RACI, policy authority and evidence of consistent decisions in affected initiatives.

Question 189

In another merger, two IT governance councils approve conflicting security standards for the same environment. Which assurance principle BEST explains the audit implication?

  1. Comparable enterprise risk assessments require transparent criteria and defensible assumptions.
  2. Governance structures must fit the current organization, decision scope and risk ownership.
  3. Management indicators are only meaningful when calculations and data sources remain controlled.
  4. Supplier management includes continuity and secure termination, not only selection and renewal.

Explanation

Correct Answer

B:

This principle explains the control or assurance implication in the second, independent scenario. Governance structures must fit the current organization, decision scope and risk ownership. The auditor should relate that principle to the observed evidence.

Incorrect Answers

A:

This is a valid consideration in enterprise risk management; the scenario instead turns on a different, more specific assurance requirement.

C:

This is a valid consideration in it performance monitoring and reporting; the scenario instead turns on a different, more specific assurance requirement.

D:

This is a valid consideration in it vendor management; the scenario instead turns on a different, more specific assurance requirement.

Question 190

In another merger, two IT governance councils approve conflicting security standards for the same environment. During a subsequent IS audit review of this issue, which unsafe assumption should the auditor challenge FIRST?

  1. A supplier's generic privacy statement is not evidence of approved processing chains.
  2. Deleting one primary record does not prove all relevant personal data was addressed.
  3. An outdated committee charter does not ensure current decisions have legitimate authority.
  4. An acceptable enterprise average does not prove every critical service meets its obligation.

Explanation

Correct Answer

C:

An outdated committee charter does not ensure current decisions have legitimate authority. The underlying issue is that governance structures must fit the current organization, decision scope and risk ownership.

Incorrect Answers

A:

That caution could matter when assessing privacy program and principles, but it is not the most immediate unsupported assumption in this case.

B:

That caution could matter when assessing privacy program and principles, but it is not the most immediate unsupported assumption in this case.

D:

That caution could matter when assessing it performance monitoring and reporting, but it is not the most immediate unsupported assumption in this case.


Certified Information Systems Auditor (CISA) Practice Tests

Purchase Individually

CISA Premium File

Premium File
CISA Premium File
1097 Q&A
$76.99$69.99

CISA Training Video Course

Training Course
CISA Training Video Course
74 Lectures
$27.49$24.99

CISA Study Guide

Study Guide
CISA Study Guide
1141 PDF Pages
$27.49$24.99

Site Search:

 

VISA, MasterCard, AmericanExpress, UnionPay

SPECIAL OFFER: GET 10% OFF

ExamCollection Premium

ExamCollection Premium Files

Pass your Exam with ExamCollection's PREMIUM files!

  • ExamCollection Certified Safe Files
  • Guaranteed to have ACTUAL Exam Questions
  • Up-to-Date Exam Study Material - Verified by Experts
  • Instant Downloads
Enter Your Email Address to Receive Your 10% Off Discount Code
A Confirmation Link will be sent to this email address to verify your login
We value your privacy. We will not rent or sell your email address

SPECIAL OFFER: GET 10% OFF

Use Discount Code:

MIN10OFF

A confirmation link was sent to your e-mail.
Please check your mailbox for a message from support@examcollection.com and follow the directions.

Next

Download Free Demo of VCE Exam Simulator

Experience Avanset VCE Exam Simulator for yourself.

Simply submit your e-mail address below to get started with our interactive software demo of your free trial.

Free Demo Limits: In the demo version you will be able to access only first 5 questions from exam.