Question 200
Functional managers and the PM both assign competing priorities to shared staff. Which caution is MOST directly relevant to the project manager's decision?
Explanation
Correct Answer
A PM in a matrix does not necessarily control an employee's entire workload. The underlying reason is that matrix organizations share authority between functional and project leaders.
Incorrect Answers
This is a caution about raci accountability, not the immediate risk in matrix authority. RACI distinguishes responsible implementers from accountable decision owners.
This is a caution about resource skills gap, not the immediate risk in matrix authority. Resource gap analysis compares available skills with project needs.
This is a caution about external resource ownership, not the immediate risk in matrix authority. External resources have different governance and allocation rules from employees.