Question 580
A service bench observes this hardware or network symptom: A server's dual redundant PSUs share one failed wall power strip and the owner assumes redundancy guarantees operation. What should the support specialist recommend FIRST within the stated limits?
- Connect redundant supplies to approved independent power paths when available.
- Recalculate the complete system power budget and select a compatible PSU with adequate headroom.
- Connect the correct CPU power lead in addition to the motherboard's 20+4-pin connector.
- Match the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement.
Explanation
Correct Answer
A:Multiple PSU modules do not protect against a common upstream electrical failure.
Incorrect Answers
B:Recalculating the complete system power budget and selecting a compatible PSU with adequate headroom would not connect redundant supplies to approved independent power paths when available.
C:Connecting the correct CPU power lead in addition to the motherboard's 20+4-pin connector would not connect redundant supplies to approved independent power paths when available.
D:Matching the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement would not connect redundant supplies to approved independent power paths when available.
Question 581
A support team must resolve TWO distinct issues at the same location, using approved non-destructive maintenance: A gaming desktop resets when its GPU reaches full load after an upgrade that substantially increased power draw. A replacement PSU has a large 24-pin motherboard connector but the user tries to leave the CPU EPS power socket unconnected. Which course of action addresses the stated issues?
- Match the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement; connect redundant supplies to approved independent power paths when available.
- Recalculate the complete system power budget and select a compatible PSU with adequate headroom; connect the correct CPU power lead in addition to the motherboard's 20+4-pin connector.
- Match the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement; connect the correct CPU power lead in addition to the motherboard's 20+4-pin connector.
- Recalculate the complete system power budget and select a compatible PSU with adequate headroom; connect redundant supplies to approved independent power paths when available.
Explanation
Correct Answer
B:For ticket (1), Peak GPU and CPU loads can exceed a supply's available continuous capacity. For ticket (2), Motherboard and CPU power inputs are separate and necessary on many systems.
Incorrect Answers
A:For ticket 1, recalculate the complete system power budget and select a compatible PSU with adequate headroom. Peak GPU and CPU loads can exceed a supply's available continuous capacity. For ticket 2, connect the correct CPU power lead in addition to the motherboard's 20+4-pin connector. Motherboard and CPU power inputs are separate and necessary on many systems.
C:For ticket 1, recalculate the complete system power budget and select a compatible PSU with adequate headroom. Peak GPU and CPU loads can exceed a supply's available continuous capacity.
D:For ticket 2, connect the correct CPU power lead in addition to the motherboard's 20+4-pin connector. Motherboard and CPU power inputs are separate and necessary on many systems.
Question 582
A support team must resolve TWO distinct issues at the same location, using approved non-destructive maintenance: A gaming desktop resets when its GPU reaches full load after an upgrade that substantially increased power draw. A technician wants to use a GPU's high-power auxiliary connector but picks a CPU EPS lead because both have eight-pin housings. Which response best addresses these needs?
- Connect the correct CPU power lead in addition to the motherboard's 20+4-pin connector; Match the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement.
- Recalculate the complete system power budget and select a compatible PSU with adequate headroom; connect redundant supplies to approved independent power paths when available.
- Connect the correct CPU power lead in addition to the motherboard's 20+4-pin connector; connect redundant supplies to approved independent power paths when available.
- Recalculate the complete system power budget and select a compatible PSU with adequate headroom; Match the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement.
Explanation
Correct Answer
D:For ticket (1), Peak GPU and CPU loads can exceed a supply's available continuous capacity. For ticket (2), CPU and GPU auxiliary cables may have different pin assignments and must not be interchanged.
Incorrect Answers
A:For ticket 1, recalculate the complete system power budget and select a compatible PSU with adequate headroom. Peak GPU and CPU loads can exceed a supply's available continuous capacity.
B:For ticket 2, match the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement. CPU and GPU auxiliary cables may have different pin assignments and must not be interchanged.
C:For ticket 1, recalculate the complete system power budget and select a compatible PSU with adequate headroom. Peak GPU and CPU loads can exceed a supply's available continuous capacity. For ticket 2, match the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement. CPU and GPU auxiliary cables may have different pin assignments and must not be interchanged.
Question 583
A support team must resolve TWO distinct issues at the same location, using approved non-destructive maintenance: A replacement PSU has a large 24-pin motherboard connector but the user tries to leave the CPU EPS power socket unconnected. A server's dual redundant PSUs share one failed wall power strip and the owner assumes redundancy guarantees operation. What is the most appropriate plan for this situation?
- Connect the correct CPU power lead in addition to the motherboard's 20+4-pin connector; connect redundant supplies to approved independent power paths when available.
- Recalculate the complete system power budget and select a compatible PSU with adequate headroom; connect redundant supplies to approved independent power paths when available.
- Connect the correct CPU power lead in addition to the motherboard's 20+4-pin connector; Match the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement.
- Recalculate the complete system power budget and select a compatible PSU with adequate headroom; Match the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement.
Explanation
Correct Answer
A:For ticket (1), Motherboard and CPU power inputs are separate and necessary on many systems. For ticket (2), Multiple PSU modules do not protect against a common upstream electrical failure.
Incorrect Answers
B:For ticket 1, connect the correct CPU power lead in addition to the motherboard's 20+4-pin connector. Motherboard and CPU power inputs are separate and necessary on many systems.
C:For ticket 2, connect redundant supplies to approved independent power paths when available. Multiple PSU modules do not protect against a common upstream electrical failure.
D:For ticket 1, connect the correct CPU power lead in addition to the motherboard's 20+4-pin connector. Motherboard and CPU power inputs are separate and necessary on many systems. For ticket 2, connect redundant supplies to approved independent power paths when available. Multiple PSU modules do not protect against a common upstream electrical failure.
Question 584
A support team must resolve TWO distinct issues at the same location, using approved non-destructive maintenance: A technician wants to use a GPU's high-power auxiliary connector but picks a CPU EPS lead because both have eight-pin housings. A server's dual redundant PSUs share one failed wall power strip and the owner assumes redundancy guarantees operation. Which course of action addresses the stated issues?
- Match the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement; connect the correct CPU power lead in addition to the motherboard's 20+4-pin connector.
- Recalculate the complete system power budget and select a compatible PSU with adequate headroom; connect the correct CPU power lead in addition to the motherboard's 20+4-pin connector.
- Match the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement; connect redundant supplies to approved independent power paths when available.
- Recalculate the complete system power budget and select a compatible PSU with adequate headroom; connect redundant supplies to approved independent power paths when available.
Explanation
Correct Answer
C:For ticket (1), CPU and GPU auxiliary cables may have different pin assignments and must not be interchanged. For ticket (2), Multiple PSU modules do not protect against a common upstream electrical failure.
Incorrect Answers
A:For ticket 2, connect redundant supplies to approved independent power paths when available. Multiple PSU modules do not protect against a common upstream electrical failure.
B:For ticket 1, match the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement. CPU and GPU auxiliary cables may have different pin assignments and must not be interchanged. For ticket 2, connect redundant supplies to approved independent power paths when available. Multiple PSU modules do not protect against a common upstream electrical failure.
D:For ticket 1, match the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement. CPU and GPU auxiliary cables may have different pin assignments and must not be interchanged.
Question 585
A service coordinator has THREE separate support tickets and needs the correct matching actions: A gaming desktop resets when its GPU reaches full load after an upgrade that substantially increased power draw. A replacement PSU has a large 24-pin motherboard connector but the user tries to leave the CPU EPS power socket unconnected. A technician wants to use a GPU's high-power auxiliary connector but picks a CPU EPS lead because both have eight-pin housings. Which response best addresses these needs?
- Recalculate the complete system power budget and select a compatible PSU with adequate headroom; connect the correct CPU power lead in addition to the motherboard's 20+4-pin connector; and Match the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement.
- Connect redundant supplies to approved independent power paths when available; connect the correct CPU power lead in addition to the motherboard's 20+4-pin connector; and Match the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement.
- Recalculate the complete system power budget and select a compatible PSU with adequate headroom; connect redundant supplies to approved independent power paths when available; and Match the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement.
- Recalculate the complete system power budget and select a compatible PSU with adequate headroom; connect the correct CPU power lead in addition to the motherboard's 20+4-pin connector; and connect redundant supplies to approved independent power paths when available.
Explanation
Correct Answer
A:For ticket (1), Peak GPU and CPU loads can exceed a supply's available continuous capacity. For ticket (2), Motherboard and CPU power inputs are separate and necessary on many systems. For ticket (3), CPU and GPU auxiliary cables may have different pin assignments and must not be interchanged.
Incorrect Answers
B:For ticket 1, recalculate the complete system power budget and select a compatible PSU with adequate headroom. Peak GPU and CPU loads can exceed a supply's available continuous capacity.
C:For ticket 2, connect the correct CPU power lead in addition to the motherboard's 20+4-pin connector. Motherboard and CPU power inputs are separate and necessary on many systems.
D:For ticket 3, match the PSU manufacturer's labeled PCIe GPU connector to the graphics card requirement. CPU and GPU auxiliary cables may have different pin assignments and must not be interchanged.
Question 586
A field technician verifies the following customer equipment condition: A cloud application is deployed in one virtual machine in one facility, and a manager calls it highly available because it is public cloud. Which response BEST addresses the actual cause or requirement?
- Add supported redundancy across suitable failure domains and test the recovery design.
- Distinguish zone redundancy from cross-region disaster recovery requirements.
- Move durable business data to an appropriate persistent managed storage service.
- Implement suitable access control, retention and recovery protections independent of platform uptime.
Explanation
Correct Answer
A:Cloud hosting location alone does not eliminate single-instance failure risks.
Incorrect Answers
B:Distinguishing zone redundancy from cross-region disaster recovery requirements would not add supported redundancy across suitable failure domains and test the recovery design.
C:Moving durable business data to an appropriate persistent managed storage service would not add supported redundancy across suitable failure domains and test the recovery design.
D:Implementing suitable access control, retention and recovery protections independent of platform uptime would not add supported redundancy across suitable failure domains and test the recovery design.
Question 587
An IT support worker is asked to resolve this case: A cloud service spreads replicas across availability zones within a region, but the customer assumes the deployment is protected against complete regional loss. Which next step MOST directly resolves the reported condition?
- Move durable business data to an appropriate persistent managed storage service.
- Implement suitable access control, retention and recovery protections independent of platform uptime.
- Add supported redundancy across suitable failure domains and test the recovery design.
- Distinguish zone redundancy from cross-region disaster recovery requirements.
Explanation
Correct Answer
D:Multiple zones reduce some local failure exposure but do not guarantee survival of all regional events.
Incorrect Answers
A:Moving durable business data to an appropriate persistent managed storage service would not distinguish zone redundancy from cross-region disaster recovery requirements.
B:Implementing suitable access control, retention and recovery protections independent of platform uptime would not distinguish zone redundancy from cross-region disaster recovery requirements.
C:Adding supported redundancy across suitable failure domains and testing the recovery design would not distinguish zone redundancy from cross-region disaster recovery requirements.
Question 588
A service bench observes this hardware or network symptom: A product team stores critical state only on each short-lived cloud instance's local scratch disk despite autoscaling. What should the support specialist recommend FIRST within the stated limits?
- Distinguish zone redundancy from cross-region disaster recovery requirements.
- Move durable business data to an appropriate persistent managed storage service.
- Implement suitable access control, retention and recovery protections independent of platform uptime.
- Add supported redundancy across suitable failure domains and test the recovery design.
Explanation
Correct Answer
B:Ephemeral instance storage may disappear when instances terminate or are replaced.
Incorrect Answers
A:Distinguishing zone redundancy from cross-region disaster recovery requirements would not move durable business data to an appropriate persistent managed storage service.
C:Implementing suitable access control, retention and recovery protections independent of platform uptime would not move durable business data to an appropriate persistent managed storage service.
D:Adding supported redundancy across suitable failure domains and testing the recovery design would not move durable business data to an appropriate persistent managed storage service.
Question 589
During a controlled office IT maintenance window, the technician notes: A user thinks that cloud-provided high availability means their own data cannot be accidentally deleted by an administrator. What is the MOST appropriate technician action?
- Move durable business data to an appropriate persistent managed storage service.
- Implement suitable access control, retention and recovery protections independent of platform uptime.
- Add supported redundancy across suitable failure domains and test the recovery design.
- Distinguish zone redundancy from cross-region disaster recovery requirements.
Explanation
Correct Answer
B:Availability SLAs do not automatically protect against authorized deletions or logical data corruption.
Incorrect Answers
A:Moving durable business data to an appropriate persistent managed storage service would not implement suitable access control, retention and recovery protections independent of platform uptime.
C:Adding supported redundancy across suitable failure domains and testing the recovery design would not implement suitable access control, retention and recovery protections independent of platform uptime.
D:Distinguishing zone redundancy from cross-region disaster recovery requirements would not implement suitable access control, retention and recovery protections independent of platform uptime.
Question 590
A support team must resolve TWO distinct issues at the same location, using approved non-destructive maintenance: A cloud application is deployed in one virtual machine in one facility, and a manager calls it highly available because it is public cloud. A cloud service spreads replicas across availability zones within a region, but the customer assumes the deployment is protected against complete regional loss. Which course of action addresses the stated issues?
- Move durable business data to an appropriate persistent managed storage service; implement suitable access control, retention and recovery protections independent of platform uptime.
- Add supported redundancy across suitable failure domains and test the recovery design; distinguish zone redundancy from cross-region disaster recovery requirements.
- Move durable business data to an appropriate persistent managed storage service; distinguish zone redundancy from cross-region disaster recovery requirements.
- Add supported redundancy across suitable failure domains and test the recovery design; implement suitable access control, retention and recovery protections independent of platform uptime.
Explanation
Correct Answer
B:For ticket (1), Cloud hosting location alone does not eliminate single-instance failure risks. For ticket (2), Multiple zones reduce some local failure exposure but do not guarantee survival of all regional events.
Incorrect Answers
A:For ticket 1, add supported redundancy across suitable failure domains and test the recovery design. Cloud hosting location alone does not eliminate single-instance failure risks. For ticket 2, distinguish zone redundancy from cross-region disaster recovery requirements. Multiple zones reduce some local failure exposure but do not guarantee survival of all regional events.
C:For ticket 1, add supported redundancy across suitable failure domains and test the recovery design. Cloud hosting location alone does not eliminate single-instance failure risks.
D:For ticket 2, distinguish zone redundancy from cross-region disaster recovery requirements. Multiple zones reduce some local failure exposure but do not guarantee survival of all regional events.
CompTIA A+ Certification Exam: Core 1 (220-1201) Practice Tests