Question 600
During the architecture review, the following case is raised: A recovery plan starts applications in random order although key management is unavailable. Which risk or unsafe assumption is most important to avoid?
Explanation
Correct Answer
Powering on front-end VMs before their identity and data services are ready cannot satisfy RTO. The warning is material because business-service restoration depends on recovering prerequisite systems in a safe sequence.
Incorrect Answers
This is a caution for criticality and workload inventory; the most relevant design boundary in the current case is bcdr dependency order.
The failback design risk is different from the incorrect assumption the architect should reject here. Business-service restoration depends on recovering prerequisite systems in a safe sequence.
The warning is material because availability zones and remote DR solve different classes of faults and may require different protection technologies. What must be demonstrated is: Powering on front-end VMs before their identity and data services are ready cannot satisfy RTO.