Question 960
A project manager must triage the following issue: A multi-supplier technology project begins contract work without documenting performance oversight, contract interfaces or commercial escalation. What initial investigation best distinguishes the causes?
Explanation
Correct Answer
Identify major contract dependencies and who has approval authority. Commercial obligations are not integrated into the project control model. The resulting action would be: Define the commercial management approach and relevant decision roles during initiation.
Incorrect Answers
Compare technician instructions with the authorized work packages. That investigation addresses board issues technical work orders; for the stated decision, examine identify major contract dependencies and who has approval authority.
Identify feasible internal, external and hybrid delivery approaches. That investigation addresses supplier selection before approach defined; for the stated decision, examine identify major contract dependencies and who has approval authority.
Inspect accepted work packages and supplier instructions. That investigation addresses unapproved team work starts; for the stated decision, examine identify major contract dependencies and who has approval authority.