Question 920
Which diagnosis best fits the project scenario: An external regulator asks the project board to add an urgent data-control feature, and the executive emails developers to implement it immediately?
Explanation
Correct Answer
Governance is implementing changes before assessing their effect on approved commitments. That cause fits the described evidence. The relevant governance rule is: A board can give ad hoc direction without bypassing issue and stage controls. The appropriate response would be to direct the project manager to assess the issue and return an authorized decision where needed.
Incorrect Answers
Termination was mistaken for permission to abandon governance and records. This could explain a different issue concerning premature closure after supplier termination, but the reported conditions instead indicate: Governance is implementing changes before assessing their effect on approved commitments.
Team estimates are no longer aligned with delegated stage control. This could explain a different issue concerning team plan conflicts with main stage, but the reported conditions instead indicate: Governance is implementing changes before assessing their effect on approved commitments.
Governance and stakeholder accountability have not been established for initiation. This could explain a different issue concerning unclear team design at startup, but the reported conditions instead indicate: Governance is implementing changes before assessing their effect on approved commitments.