Question 890
A stage review identifies: An internal sponsor demands a full data-centre relocation within ten days though statutory permits take longer than that. Which weakness in control or decision-making is most likely?
Explanation
Correct Answer
An untested mandate deadline would make the preliminary project infeasible. That cause fits the described evidence. The relevant governance rule is: Starting up screens for a viable approach before spending heavily on initiation. The appropriate response would be to test feasibility and surface the constraint in the outline business case, approach and brief before proceeding.
Incorrect Answers
Initiation produced discussion rather than a decision-ready control baseline. This could explain a different issue concerning no control baseline in pid, but the reported conditions instead indicate: An untested mandate deadline would make the preliminary project infeasible.
Closing work focuses on construction rather than approved sustainability outcomes. This could explain a different issue concerning final sustainability outcome not evaluated, but the reported conditions instead indicate: An untested mandate deadline would make the preliminary project infeasible.
Team estimates are no longer aligned with delegated stage control. This could explain a different issue concerning team plan conflicts with main stage, but the reported conditions instead indicate: An untested mandate deadline would make the preliminary project infeasible.