Question 350
A stage review identifies: A workstream manager decides to change the project's business objectives in order to simplify its own delivery commitments. Which weakness in control or decision-making is most likely?
Explanation
Correct Answer
Delivery accountability is being confused with direction of project objectives. That cause fits the described evidence. The relevant governance rule is: Defined roles separate strategic direction, day-to-day project management and product delivery. The appropriate response would be to return strategic objective changes to the project board while the team manager governs accepted work packages.
Incorrect Answers
A replacement baseline has been used without authorized exception direction. This could explain a different issue concerning exception plan not authorized before use, but the reported conditions instead indicate: Delivery accountability is being confused with direction of project objectives.
An issue's urgency is being mistaken for a tolerance exception. This could explain a different issue concerning urgent issue confused with exception, but the reported conditions instead indicate: Delivery accountability is being confused with direction of project objectives.
Assurance of process compliance is being confused with verification of product quality. This could explain a different issue concerning quality assurance independent of project, but the reported conditions instead indicate: Delivery accountability is being confused with direction of project objectives.