Question 300
Before escalating a proposed solution, what should be checked about: A new privacy requirement increases likely fines and remediation costs for a customer data project, but its forecast still excludes the exposure?
- Compare new legal risk estimates with the business case contingency and options
- Compare material risk register exposure with last highlight report
- Compare recorded pilot defect frequency with the original risk assumptions
- Calculate the probable restoration lead time using supplier and logistics data
Explanation
Correct Answer
A:Compare new legal risk estimates with the business case contingency and options. Investment forecasts no longer reflect the project's significant risk profile. The resulting action would be: Reassess risks, compliance costs and options within the business case and escalate material changes.
Incorrect Answers
B:Compare material risk register exposure with last highlight report. That investigation addresses risk tolerance data missing from highlight; for the stated decision, compare new legal risk estimates with the business case contingency and options.
C:Compare recorded pilot defect frequency with the original risk assumptions. That investigation addresses probability changes after pilot; for the stated decision, compare new legal risk estimates with the business case contingency and options.
D:Calculate the probable restoration lead time using supplier and logistics data. That investigation addresses contingency covers costs but not response time; for the stated decision, compare new legal risk estimates with the business case contingency and options.
Question 301
In this project scenario—A prototype proves that the core sensor cannot reach required accuracy, but the board demands completing the remaining rollout because the first stage was expensive—what is the most appropriate management action?
- Present evidence that the forecast value is no longer achievable and recommend stopping or changing the project
- Obtain authorization through the agreed project board arrangements rather than acting beyond delegated authority
- Give the change authority explicit delegated limits and escalation rules
- Record the potential supplier failure as a risk, assess exposure and agree a proportionate response owner
Explanation
Correct Answer
A:Present evidence that the forecast value is no longer achievable and recommend stopping or changing the project. Sunk cost is being treated as a reason to continue an unjustified investment. Business justification is prospective and must not be driven by sunk-cost bias.
Incorrect Answers
B:Obtain authorization through the agreed project board arrangements rather than acting beyond delegated authority. It applies to executive delegates investment decision downwards; the current decision depends on this finding: Sunk cost is being treated as a reason to continue an unjustified investment.
C:Give the change authority explicit delegated limits and escalation rules. It applies to change authority with no limits; the current decision depends on this finding: Sunk cost is being treated as a reason to continue an unjustified investment.
D:Record the potential supplier failure as a risk, assess exposure and agree a proportionate response owner. It applies to potential supplier insolvency not logged; the current decision depends on this finding: Sunk cost is being treated as a reason to continue an unjustified investment.
Question 302
A team reflects on this failure: A prototype proves that the core sensor cannot reach required accuracy, but the board demands completing the remaining rollout because the first stage was expensive. What is the most relevant underlying problem?
- Sunk cost is being treated as a reason to continue an unjustified investment
- Local change approval has been granted without protecting the board's tolerance authority
- A possible future uncertainty is being ignored until it becomes an actual issue
- The business investment decision is being pushed below the board's mandate
Explanation
Correct Answer
A:Sunk cost is being treated as a reason to continue an unjustified investment. That cause fits the described evidence. The relevant governance rule is: Business justification is prospective and must not be driven by sunk-cost bias. The appropriate response would be to present evidence that the forecast value is no longer achievable and recommend stopping or changing the project.
Incorrect Answers
B:Local change approval has been granted without protecting the board's tolerance authority. This could explain a different issue concerning change authority with no limits, but the reported conditions instead indicate: Sunk cost is being treated as a reason to continue an unjustified investment.
C:A possible future uncertainty is being ignored until it becomes an actual issue. This could explain a different issue concerning potential supplier insolvency not logged, but the reported conditions instead indicate: Sunk cost is being treated as a reason to continue an unjustified investment.
D:The business investment decision is being pushed below the board's mandate. This could explain a different issue concerning executive delegates investment decision downwards, but the reported conditions instead indicate: Sunk cost is being treated as a reason to continue an unjustified investment.
Question 303
After correcting this project problem—A prototype proves that the core sensor cannot reach required accuracy, but the board demands completing the remaining rollout because the first stage was expensive—which result would best show that the correction worked?
- The decision compares future costs and feasible value rather than historical spend
- Stage funding is authorized by the project board and properly recorded
- The risk register contains likelihood, impact, owner and planned response with review date
- In-tolerance changes follow delegation and outside-tolerance proposals reach the correct decision level
Explanation
Correct Answer
A:The decision compares future costs and feasible value rather than historical spend. This is the observable outcome expected after the action: Present evidence that the forecast value is no longer achievable and recommend stopping or changing the project. It tests the weakness that sunk cost is being treated as a reason to continue an unjustified investment.
Incorrect Answers
B:Stage funding is authorized by the project board and properly recorded. That would verify executive delegates investment decision downwards, not the outcome at issue. The evidence needed for this situation is: The decision compares future costs and feasible value rather than historical spend.
C:The risk register contains likelihood, impact, owner and planned response with review date. That would verify potential supplier insolvency not logged, not the outcome at issue. The evidence needed for this situation is: The decision compares future costs and feasible value rather than historical spend.
D:In-tolerance changes follow delegation and outside-tolerance proposals reach the correct decision level. That would verify change authority with no limits, not the outcome at issue. The evidence needed for this situation is: The decision compares future costs and feasible value rather than historical spend.
Question 304
An instructor asks why the proposed management control is justified for: A prototype proves that the core sensor cannot reach required accuracy, but the board demands completing the remaining rollout because the first stage was expensive. Which explanation is most relevant?
- Decision delegation must align with project-level authority and tolerance thresholds
- The executive leads business justification while the project manager manages authorized work
- Business justification is prospective and must not be driven by sunk-cost bias
- Risk management addresses uncertain future events that could affect objectives
Explanation
Correct Answer
C:Business justification is prospective and must not be driven by sunk-cost bias. This principle matters here because sunk cost is being treated as a reason to continue an unjustified investment. The response should tackle the stated project-control deficiency.
Incorrect Answers
A:Decision delegation must align with project-level authority and tolerance thresholds. That principle is more directly associated with change authority with no limits. The present case concerns the weakness that sunk cost is being treated as a reason to continue an unjustified investment.
B:The executive leads business justification while the project manager manages authorized work. That principle is more directly associated with executive delegates investment decision downwards. The present case concerns the weakness that sunk cost is being treated as a reason to continue an unjustified investment.
D:Risk management addresses uncertain future events that could affect objectives. That principle is more directly associated with potential supplier insolvency not logged. The present case concerns the weakness that sunk cost is being treated as a reason to continue an unjustified investment.
Question 305
To keep the project from repeating this problem—A prototype proves that the core sensor cannot reach required accuracy, but the board demands completing the remaining rollout because the first stage was expensive—which control is most useful?
- Define feasibility kill criteria before expensive implementation
- Periodically audit delegated change decisions against limits
- Publish decision delegation rules for board absences
- Review key supplier financial and delivery indicators during each stage
Explanation
Correct Answer
A:Define feasibility kill criteria before expensive implementation. That preventive control addresses a repeated failure in which sunk cost is being treated as a reason to continue an unjustified investment. Effectiveness can be checked by: The decision compares future costs and feasible value rather than historical spend.
Incorrect Answers
B:Periodically audit delegated change decisions against limits. It can prevent change authority with no limits, but it does not control the stated recurrence risk: Sunk cost is being treated as a reason to continue an unjustified investment.
C:Publish decision delegation rules for board absences. It can prevent executive delegates investment decision downwards, but it does not control the stated recurrence risk: Sunk cost is being treated as a reason to continue an unjustified investment.
D:Review key supplier financial and delivery indicators during each stage. It can prevent potential supplier insolvency not logged, but it does not control the stated recurrence risk: Sunk cost is being treated as a reason to continue an unjustified investment.
Question 306
Which first piece of evidence best helps understand this situation: A prototype proves that the core sensor cannot reach required accuracy, but the board demands completing the remaining rollout because the first stage was expensive?
- Review prototype accuracy against minimum viability thresholds
- Examine the supplier's current viability evidence and contractual recovery options
- Inspect the documented change authority mandate and tolerance table
- Check who has authority to commit next-stage funding
Explanation
Correct Answer
A:Review prototype accuracy against minimum viability thresholds. Sunk cost is being treated as a reason to continue an unjustified investment. The resulting action would be: Present evidence that the forecast value is no longer achievable and recommend stopping or changing the project.
Incorrect Answers
B:Examine the supplier's current viability evidence and contractual recovery options. That investigation addresses potential supplier insolvency not logged; for the stated decision, review prototype accuracy against minimum viability thresholds.
C:Inspect the documented change authority mandate and tolerance table. That investigation addresses change authority with no limits; for the stated decision, review prototype accuracy against minimum viability thresholds.
D:Check who has authority to commit next-stage funding. That investigation addresses executive delegates investment decision downwards; for the stated decision, review prototype accuracy against minimum viability thresholds.
Question 307
A delivery lead describes this project difficulty: A data archival project has no direct revenue benefit, and finance rejects it without considering the mandatory regulator deadline. Which response best fits the method?
- Reassign suitable risk accountability and delegate response execution to those able to act
- Execute the defined tests and compare measured performance with the allowed range
- Update the project management team structure and role descriptions to include operational handover ownership
- Record compliance risk avoidance and legal necessity as valid noncash justification in the business case
Explanation
Correct Answer
D:Record compliance risk avoidance and legal necessity as valid noncash justification in the business case. Value assessment excludes obligatory outcomes that do not create revenue. A business case can be driven by mandatory compliance and risk reduction as well as cash return.
Incorrect Answers
A:Reassign suitable risk accountability and delegate response execution to those able to act. It applies to risk owner cannot influence response; the current decision depends on this finding: Value assessment excludes obligatory outcomes that do not create revenue.
B:Execute the defined tests and compare measured performance with the allowed range. It applies to quality tolerance assumed to mean no checking; the current decision depends on this finding: Value assessment excludes obligatory outcomes that do not create revenue.
C:Update the project management team structure and role descriptions to include operational handover ownership. It applies to stakeholder groups omitted from responsibilities; the current decision depends on this finding: Value assessment excludes obligatory outcomes that do not create revenue.
Question 308
Which diagnosis best fits the project scenario: A data archival project has no direct revenue benefit, and finance rejects it without considering the mandatory regulator deadline?
- A future operational accountability gap is hidden from governance planning
- Value assessment excludes obligatory outcomes that do not create revenue
- Risk ownership was allocated without the authority or access needed to manage it
- The existence of tolerance has been mistaken for evidence of compliance
Explanation
Correct Answer
B:Value assessment excludes obligatory outcomes that do not create revenue. That cause fits the described evidence. The relevant governance rule is: A business case can be driven by mandatory compliance and risk reduction as well as cash return. The appropriate response would be to record compliance risk avoidance and legal necessity as valid noncash justification in the business case.
Incorrect Answers
A:A future operational accountability gap is hidden from governance planning. This could explain a different issue concerning stakeholder groups omitted from responsibilities, but the reported conditions instead indicate: Value assessment excludes obligatory outcomes that do not create revenue.
C:Risk ownership was allocated without the authority or access needed to manage it. This could explain a different issue concerning risk owner cannot influence response, but the reported conditions instead indicate: Value assessment excludes obligatory outcomes that do not create revenue.
D:The existence of tolerance has been mistaken for evidence of compliance. This could explain a different issue concerning quality tolerance assumed to mean no checking, but the reported conditions instead indicate: Value assessment excludes obligatory outcomes that do not create revenue.
Question 309
In a project health review, what outcome would validate resolution of: A data archival project has no direct revenue benefit, and finance rejects it without considering the mandatory regulator deadline?
- The approved justification recognizes the regulatory requirement, cost and realistic solution
- The appointed owner can influence treatment and report forecast exposure
- The nominated department accepts the post-project stewardship role before go-live
- Actual measurements demonstrate the product is within the approved quality range
Explanation
Correct Answer
A:The approved justification recognizes the regulatory requirement, cost and realistic solution. This is the observable outcome expected after the action: Record compliance risk avoidance and legal necessity as valid noncash justification in the business case. It tests the weakness that value assessment excludes obligatory outcomes that do not create revenue.
Incorrect Answers
B:The appointed owner can influence treatment and report forecast exposure. That would verify risk owner cannot influence response, not the outcome at issue. The evidence needed for this situation is: The approved justification recognizes the regulatory requirement, cost and realistic solution.
C:The nominated department accepts the post-project stewardship role before go-live. That would verify stakeholder groups omitted from responsibilities, not the outcome at issue. The evidence needed for this situation is: The approved justification recognizes the regulatory requirement, cost and realistic solution.
D:Actual measurements demonstrate the product is within the approved quality range. That would verify quality tolerance assumed to mean no checking, not the outcome at issue. The evidence needed for this situation is: The approved justification recognizes the regulatory requirement, cost and realistic solution.
Question 310
Which PRINCE2 management principle or mechanism best explains the appropriate response to: A data archival project has no direct revenue benefit, and finance rejects it without considering the mandatory regulator deadline?
- Organizing includes relationships with business-as-usual roles that will receive products
- Risk owners should be able to manage uncertainty and coordinate response actions
- A business case can be driven by mandatory compliance and risk reduction as well as cash return
- A tolerance sets an acceptable variation; evidence is still needed to establish conformity
Explanation
Correct Answer
C:A business case can be driven by mandatory compliance and risk reduction as well as cash return. This principle matters here because value assessment excludes obligatory outcomes that do not create revenue. The response should tackle the stated project-control deficiency.
Incorrect Answers
A:Organizing includes relationships with business-as-usual roles that will receive products. That principle is more directly associated with stakeholder groups omitted from responsibilities. The present case concerns the weakness that value assessment excludes obligatory outcomes that do not create revenue.
B:Risk owners should be able to manage uncertainty and coordinate response actions. That principle is more directly associated with risk owner cannot influence response. The present case concerns the weakness that value assessment excludes obligatory outcomes that do not create revenue.
D:A tolerance sets an acceptable variation; evidence is still needed to establish conformity. That principle is more directly associated with quality tolerance assumed to mean no checking. The present case concerns the weakness that value assessment excludes obligatory outcomes that do not create revenue.