Question 190
For the project situation—A project manager sends optimistic one-page updates that omit a rising risk exposure and the board assumes the stage remains healthy—which underlying method concept should guide the decision?
Explanation
Correct Answer
Governance communication must support informed decisions even when news is adverse. This principle matters here because reporting has been optimized for reassurance rather than decision-quality. The response should tackle the stated project-control deficiency.
Incorrect Answers
Governance leadership should empower appropriate managerial roles rather than micro-manage teams. That principle is more directly associated with executive overdirects day-to-day team. The present case concerns the weakness that reporting has been optimized for reassurance rather than decision-quality.
Managing organizational change requires outcomes and adoption evidence rather than activity counts. That principle is more directly associated with sponsor assumes training equals adoption. The present case concerns the weakness that reporting has been optimized for reassurance rather than decision-quality.
Decision evidence should reflect both delivery and people consequences. That principle is more directly associated with people readiness not reflected in stage gate. The present case concerns the weakness that reporting has been optimized for reassurance rather than decision-quality.