Question 150
For this project problem—A board executive changes daily technical assignments through direct messages, bypassing the project manager and causing contradictory instructions—which initial review would most directly focus the response?
Explanation
Correct Answer
Review the history of conflicting work instructions and their sources. Informal command is undermining defined responsibilities and team autonomy. The resulting action would be: Reinforce agreed leadership, delegation and delivery communication through the project manager and team manager.
Incorrect Answers
Search for contradictory approval messages and identify the authorized decision maker. That investigation addresses decision buried in chat thread; for the stated decision, review the history of conflicting work instructions and their sources.
Compare project log risk scores with the latest highlight report. That investigation addresses board updates hide bad news; for the stated decision, review the history of conflicting work instructions and their sources.
Interview regional teams about their interpretation of dates and obligations. That investigation addresses multilingual rollout misunderstanding; for the stated decision, review the history of conflicting work instructions and their sources.