Question 730
In this security management situation: A chemical plant assigns a final deadline to every safeguard without identifying technology dependencies. What should the organization establish operationally?
Explanation
Correct Answer
Define tasks, prerequisites, resourcing, milestones, residual-risk reassessment and owner approval. This design addresses the issue that a chemical plant assigns a final deadline to every safeguard without identifying technology dependencies. It implements the decision to plan control implementation with accountable ownership, resources, timing and verification. Verify that progress records show completion and tested effectiveness against the treatment plan. A failure would be treating a risk register entry as an actionable deployment plan without owners or dates.
Incorrect Answers
Record operating model, technology, legal environment, competition and change drivers with periodic review. That approach concerns context and external factors, as when an energy company deploys connected devices without reassessing regulatory and supply-chain context. This case instead requires the team to define tasks, prerequisites, resourcing, milestones, residual-risk reassessment and owner approval. The remaining risk is unfulfilled treatment commitments and uncontrolled late delivery. Case: A chemical plant assigns a final deadline to every safeguard without identifying technology dependencies.
Rank unacceptable exposures for treatment with owner sign-off and transparent escalation. That approach concerns risk evaluation and treatment priority, as when a bank treats low-impact workstation risks before highly rated payment service exposures for political reasons. This case instead requires the team to define tasks, prerequisites, resourcing, milestones, residual-risk reassessment and owner approval. The remaining risk is unfulfilled treatment commitments and uncontrolled late delivery. Case: A chemical plant assigns a final deadline to every safeguard without identifying technology dependencies.
Maintain stakeholder needs, binding commitments and mapped organizational responses. That approach concerns interested-party needs, as when a fintech builds safeguards for internal operations but overlooks payment-partner notification obligations. This case instead requires the team to define tasks, prerequisites, resourcing, milestones, residual-risk reassessment and owner approval. The remaining risk is unfulfilled treatment commitments and uncontrolled late delivery. Case: A chemical plant assigns a final deadline to every safeguard without identifying technology dependencies.