Question 280
Which continuous-control step should be adopted after resolving: An AIMS program has a target certification date but no intermediate deliverables or dependency sequence?
Explanation
Correct Answer
Update milestone dependencies after scope or resource changes. This prevention step addresses the recurring weakness: a single end date cannot reveal schedule feasibility or blocker dependencies. Continued assurance should verify that the plan tracks scope, policy, risk treatment, operational controls, and readiness deliverables.
Incorrect Answers
Check indicator definitions before the first reporting period. That safeguard would help prevent objective metrics design problems, but the current incident arises because a single end date cannot reveal schedule feasibility or blocker dependencies.
Review supplier interfaces at contract renewal and system change. That safeguard would help prevent scope boundary for suppliers problems, but the current incident arises because a single end date cannot reveal schedule feasibility or blocker dependencies.
Keep revision control active throughout project execution. That safeguard would help prevent AIMS project records problems, but the current incident arises because a single end date cannot reveal schedule feasibility or blocker dependencies.