Question 500
Another group has cross-project release automation without a reliable parent-child execution trace. Which unsupported assumption should the engineer challenge FIRST?
Explanation
Correct Answer
A downstream green status does not prove it deployed the artifact produced by the expected upstream run. This is the relevant unsupported assumption because chained pipelines need explicit provenance to preserve release traceability across orchestration boundaries.
Incorrect Answers
A successful Functions deployment does not guarantee that in-flight messages can be read by the new version. The relevant evidence instead is: A downstream green status does not prove it deployed the artifact produced by the expected upstream run.
This is the relevant unsupported assumption because managed package feeds make dependencies reusable and traceable when versions and credentials are controlled. The acceptance criterion here is: A downstream green status does not prove it deployed the artifact produced by the expected upstream run.
This is the relevant unsupported assumption because artifact retention should preserve evidence and rollback capability without retaining every temporary file forever. What must be demonstrated is: A downstream green status does not prove it deployed the artifact produced by the expected upstream run.