Pass Your Microsoft AZ-305 Exam Easy!

Microsoft AZ-305 Exam Questions & Answers, Accurate & Verified By IT Experts

Instant Download, Free Fast Updates, 99.6% Pass Rate

AZ-305 Premium Bundle

$79.99

Microsoft AZ-305 Premium Bundle

AZ-305 Premium File: 382 Questions & Answers

Last Update: Oct 14, 2026

AZ-305 Training Course: 87 Video Lectures

AZ-305 PDF Study Guide: 933 Pages

AZ-305 Bundle gives you unlimited access to "AZ-305" files. However, this does not replace the need for a .vce exam simulator. To download VCE exam simulator click here
Microsoft AZ-305 Premium Bundle
Microsoft AZ-305 Premium Bundle

AZ-305 Premium File: 382 Questions & Answers

Last Update: Oct 14, 2026

AZ-305 Training Course: 87 Video Lectures

AZ-305 PDF Study Guide: 933 Pages

$79.99

AZ-305 Bundle gives you unlimited access to "AZ-305" files. However, this does not replace the need for a .vce exam simulator. To download your .vce exam simulator click here

Microsoft AZ-305 Practice Test 65

Question 640

A design review identifies: A high-throughput Azure Functions workload must stay responsive with prewarmed instances and VNet integration under variable demand. The failure is: Critical function executions time out after large cold starts and lack required networking features. Select TWO distinct decisions that together provide the immediate technical solution AND an ongoing prevention control. A verification-only step does not replace either responsibility.

  1. Enable and design around Service Bus Premium availability zone resilience with redundant consumers.
  2. Use App Service zone redundancy with a supporting plan and region where available, then configure sufficient instances.
  3. Test plan scaling, zone support and function retry semantics after runtime upgrades.
  4. Use a supported Functions hosting plan such as Elastic Premium with appropriate warm instances and zone capabilities where required.
  5. Monitor zonal capacity and load balancer health probes during scale changes.

Explanation

Correct Answers

C:

The key follow-up control is: Test plan scaling, zone support and function retry semantics after runtime upgrades. It avoids recurrence of the scenario in which: Critical function executions time out after large cold starts and lack required networking features. It addresses: The hosting plan does not meet warm-instance and networking requirements.

D:

This option addresses the actual design defect: The hosting plan does not meet warm-instance and networking requirements. The correction is: Use a supported Functions hosting plan such as Elastic Premium with appropriate warm instances and zone capabilities where required. Confirm the outcome with: Send burst traffic and validate cold-start/latency and VNet connectivity under scale changes.

Incorrect Answers

A:

That design instead addresses another observed condition: A single-zone dependent messaging tier becomes unavailable during zonal maintenance. Its technical cause is: The messaging service tier/configuration does not meet zonal resilience requirements. The current workload exhibits: Critical function executions time out after large cold starts and lack required networking features. Its targeted remedy is: Use a supported Functions hosting plan such as Elastic Premium with appropriate warm instances and zone capabilities where required.

B:

This choice mitigates an alternative scenario, where: Both instances are unavailable when their single shared zone has an incident. The underlying issue there is: Scale-out count was confused with physical availability-zone placement. Here the root issue is: The hosting plan does not meet warm-instance and networking requirements. Choose the corresponding action: Use a supported Functions hosting plan such as Elastic Premium with appropriate warm instances and zone capabilities where required.

E:

This is a reasonable safeguard for a different fault: All stateless app instances are placed in one zone and fail together. That different mechanism is: The compute deployment lacks redundant zonal placement and health-based load balancing. The original incident here instead arises from: The hosting plan does not meet warm-instance and networking requirements. The directly relevant safeguard is: Test plan scaling, zone support and function retry semantics after runtime upgrades.

Question 641

A design workshop has this requirement: A globally distributed app needs Redis-like caching for availability across regional outages without treating cache as the authoritative database. Operators currently observe: A cache outage causes irreversible loss of authoritative session/customer records. Select the ONE design remedy that best addresses the root cause.

  1. Design an eligible managed Redis caching solution with documented replication/failover, plus resilient data-source fallback.
  2. Design multi-region entry routing, compatible identity dependencies and replicated application configuration/secrets for the failover region.
  3. Enable the supported zone-redundant configuration for the Azure SQL tier and region.
  4. Deploy application-level high availability or availability-zone/VM redundancy for routine failures, with ASR reserved for DR.

Explanation

Correct Answer

A:

The evidence (A cache outage causes irreversible loss of authoritative session/customer records.) identifies the following cause: Ephemeral cache was treated as the only durable data system. The design that removes it is: Design an eligible managed Redis caching solution with documented replication/failover, plus resilient data-source fallback. The acceptance check is: Fail the primary cache and confirm the application can miss and rehydrate from its source of truth.

Incorrect Answers

B:

The option belongs to a different failure mechanism: Regional failover planning omitted shared identity/configuration dependencies and allowed network paths. That situation exhibits: The secondary web app serves static pages but authentication and configuration retrieval fail. For the stated case, the remedy is: Design an eligible managed Redis caching solution with documented replication/failover, plus resilient data-source fallback.

C:

That design instead addresses another observed condition: Single-zone database deployment becomes unavailable during a zonal outage. Its technical cause is: Zone redundancy was not enabled for an eligible database deployment. The current workload exhibits: A cache outage causes irreversible loss of authoritative session/customer records. Its targeted remedy is: Design an eligible managed Redis caching solution with documented replication/failover, plus resilient data-source fallback.

D:

This choice mitigates an alternative scenario, where: Routine host outages cause long interruptions while region recovery replication remains healthy. The underlying issue there is: Disaster recovery orchestration does not substitute for continuous local high availability. Here the root issue is: Ephemeral cache was treated as the only durable data system. Choose the corresponding action: Design an eligible managed Redis caching solution with documented replication/failover, plus resilient data-source fallback.

Question 642

The planned architecture is: Design an eligible managed Redis caching solution with documented replication/failover, plus resilient data-source fallback. Workload context: A globally distributed app needs Redis-like caching for availability across regional outages without treating cache as the authoritative database. Which acceptance test demonstrates that the required behavior works?

  1. Deactivate primary DNS/routing and verify secondary web login and Key Vault configuration still function.
  2. Validate zone redundancy setting and failover behavior under the service's supported test methods.
  3. Simulate a host failure and verify service continues without manual recovery orchestration.
  4. Fail the primary cache and confirm the application can miss and rehydrate from its source of truth.

Explanation

Correct Answer

D:

The acceptance test is specific: Fail the primary cache and confirm the application can miss and rehydrate from its source of truth. Its purpose is to establish that the proposed architecture works: Design an eligible managed Redis caching solution with documented replication/failover, plus resilient data-source fallback.

Incorrect Answers

A:

That observation pertains to a separate failure: The secondary web app serves static pages but authentication and configuration retrieval fail. Its cause is: Regional failover planning omitted shared identity/configuration dependencies and allowed network paths. It does not confirm the result of this design. The direct proof would be: Fail the primary cache and confirm the application can miss and rehydrate from its source of truth.

B:

The alternative test targets: Enable the supported zone-redundant configuration for the Azure SQL tier and region. The scenario's actual proposed remedy is: Design an eligible managed Redis caching solution with documented replication/failover, plus resilient data-source fallback. Verify that one by: Fail the primary cache and confirm the application can miss and rehydrate from its source of truth.

C:

This check validates a different workload: Simulate a host failure and verify service continues without manual recovery orchestration. Its associated design is: Deploy application-level high availability or availability-zone/VM redundancy for routine failures, with ASR reserved for DR. The required acceptance test here is: Fail the primary cache and confirm the application can miss and rehydrate from its source of truth.

Question 643

The customer states: A globally distributed app needs Redis-like caching for availability across regional outages without treating cache as the authoritative database. An incident reveals: A cache outage causes irreversible loss of authoritative session/customer records. What cause best accounts for this evidence?

  1. Zone redundancy was not enabled for an eligible database deployment.
  2. Regional failover planning omitted shared identity/configuration dependencies and allowed network paths.
  3. Disaster recovery orchestration does not substitute for continuous local high availability.
  4. Ephemeral cache was treated as the only durable data system.

Explanation

Correct Answer

D:

This is the failure mechanism rather than an incidental symptom: Ephemeral cache was treated as the only durable data system. It accounts for: A cache outage causes irreversible loss of authoritative session/customer records. The architectural repair is: Design an eligible managed Redis caching solution with documented replication/failover, plus resilient data-source fallback.

Incorrect Answers

A:

The proposed diagnosis fits another scenario: Zone redundancy was not enabled for an eligible database deployment. It would typically be reflected by: Single-zone database deployment becomes unavailable during a zonal outage. The current evidence instead supports: Ephemeral cache was treated as the only durable data system.

B:

The alternative weakness is: Regional failover planning omitted shared identity/configuration dependencies and allowed network paths. Its associated failure is: The secondary web app serves static pages but authentication and configuration retrieval fail. Neither explains the present observation: A cache outage causes irreversible loss of authoritative session/customer records. The direct cause here is: Ephemeral cache was treated as the only durable data system.

C:

This cause would explain a different symptom: Routine host outages cause long interruptions while region recovery replication remains healthy. The mechanism for that event is: Disaster recovery orchestration does not substitute for continuous local high availability. Here the stated symptom is: A cache outage causes irreversible loss of authoritative session/customer records. Its cause is: Ephemeral cache was treated as the only durable data system.

Question 644

Workload context: A globally distributed app needs Redis-like caching for availability across regional outages without treating cache as the authoritative database. The implemented remedy is: Design an eligible managed Redis caching solution with documented replication/failover, plus resilient data-source fallback. Which ongoing practice most specifically prevents recurrence of this failure: A cache outage causes irreversible loss of authoritative session/customer records.?

  1. Run complete synthetic login and settings tests against each region during continuity reviews.
  2. Review cache failover behavior and app fallback under simulated disconnection.
  3. Test routine fault tolerance independently of regional DR recovery plans.
  4. Review the tier and region's zone support before database scaling or migration.

Explanation

Correct Answer

B:

The key follow-up control is: Review cache failover behavior and app fallback under simulated disconnection. It avoids recurrence of the scenario in which: A cache outage causes irreversible loss of authoritative session/customer records. It addresses: Ephemeral cache was treated as the only durable data system.

Incorrect Answers

A:

This is a reasonable safeguard for a different fault: The secondary web app serves static pages but authentication and configuration retrieval fail. That different mechanism is: Regional failover planning omitted shared identity/configuration dependencies and allowed network paths. The original incident here instead arises from: Ephemeral cache was treated as the only durable data system. The directly relevant safeguard is: Review cache failover behavior and app fallback under simulated disconnection.

C:

That safeguard manages another risk: Disaster recovery orchestration does not substitute for continuous local high availability. Its scenario is: Routine host outages cause long interruptions while region recovery replication remains healthy. The present recurring risk is: Ephemeral cache was treated as the only durable data system. The proper ongoing control is: Review cache failover behavior and app fallback under simulated disconnection.

D:

This is a reasonable safeguard for a different fault: Single-zone database deployment becomes unavailable during a zonal outage. That different mechanism is: Zone redundancy was not enabled for an eligible database deployment. The original incident here instead arises from: Ephemeral cache was treated as the only durable data system. The directly relevant safeguard is: Review cache failover behavior and app fallback under simulated disconnection.

Question 645

A solution architect is reviewing a workload: An Azure Database for PostgreSQL flexible-server production database must fail over within the region after a zone loss. The observed incident is: The server stays unavailable while a single-zone host is repaired. Which architecture choice most directly removes the identified weakness?

  1. Implement application-side retry and reconnect using the stable MySQL flexible-server hostname with suitable timeouts/backoff, while keeping the managed HA deployment.
  2. Enable and design around Service Bus Premium availability zone resilience with redundant consumers.
  3. Enable supported zone-redundant high availability with managed standby and compatible compute/region selection.
  4. Enable the supported zone-redundant configuration for the Azure SQL tier and region.

Explanation

Correct Answer

C:

The evidence (The server stays unavailable while a single-zone host is repaired.) identifies the following cause: No eligible zone-redundant PostgreSQL standby was provisioned. The design that removes it is: Enable supported zone-redundant high availability with managed standby and compatible compute/region selection. The acceptance check is: Inspect HA role, observe reconnect after a controlled test and validate data consistency.

Incorrect Answers

A:

The option belongs to a different failure mechanism: The client connection pool lacks robust reconnect and DNS refresh behavior after a managed database failover. That situation exhibits: A MySQL failover finishes but the API continues failing with stale database connections until every application instance is restarted. For the stated case, the remedy is: Enable supported zone-redundant high availability with managed standby and compatible compute/region selection.

B:

That design instead addresses another observed condition: A single-zone dependent messaging tier becomes unavailable during zonal maintenance. Its technical cause is: The messaging service tier/configuration does not meet zonal resilience requirements. The current workload exhibits: The server stays unavailable while a single-zone host is repaired. Its targeted remedy is: Enable supported zone-redundant high availability with managed standby and compatible compute/region selection.

D:

The option belongs to a different failure mechanism: Zone redundancy was not enabled for an eligible database deployment. That situation exhibits: Single-zone database deployment becomes unavailable during a zonal outage. For the stated case, the remedy is: Enable supported zone-redundant high availability with managed standby and compatible compute/region selection.

Question 646

An architect proposes this change: Enable supported zone-redundant high availability with managed standby and compatible compute/region selection. The workload context is: An Azure Database for PostgreSQL flexible-server production database must fail over within the region after a zone loss. Which evidence would most directly validate the change?

  1. Trigger a controlled failover and confirm database clients reconnect and restore successful transactions without manually replacing server IPs.
  2. Inspect HA role, observe reconnect after a controlled test and validate data consistency.
  3. Validate zone redundancy setting and failover behavior under the service's supported test methods.
  4. Disable a processing node or zone in tests and confirm queues and receivers remain serviceable within the regional SLA.

Explanation

Correct Answer

B:

This observation directly verifies the intended design: Inspect HA role, observe reconnect after a controlled test and validate data consistency. The architecture being tested is: Enable supported zone-redundant high availability with managed standby and compatible compute/region selection. The original symptom was: The server stays unavailable while a single-zone host is repaired.

Incorrect Answers

A:

The alternative test targets: Implement application-side retry and reconnect using the stable MySQL flexible-server hostname with suitable timeouts/backoff, while keeping the managed HA deployment. The scenario's actual proposed remedy is: Enable supported zone-redundant high availability with managed standby and compatible compute/region selection. Verify that one by: Inspect HA role, observe reconnect after a controlled test and validate data consistency.

C:

That observation pertains to a separate failure: Single-zone database deployment becomes unavailable during a zonal outage. Its cause is: Zone redundancy was not enabled for an eligible database deployment. It does not confirm the result of this design. The direct proof would be: Inspect HA role, observe reconnect after a controlled test and validate data consistency.

D:

The alternative test targets: Enable and design around Service Bus Premium availability zone resilience with redundant consumers. The scenario's actual proposed remedy is: Enable supported zone-redundant high availability with managed standby and compatible compute/region selection. Verify that one by: Inspect HA role, observe reconnect after a controlled test and validate data consistency.

Question 647

During architecture troubleshooting, a team reports: The server stays unavailable while a single-zone host is repaired. Context: An Azure Database for PostgreSQL flexible-server production database must fail over within the region after a zone loss. Which underlying design mistake explains the observed behavior most precisely?

  1. The messaging service tier/configuration does not meet zonal resilience requirements.
  2. The client connection pool lacks robust reconnect and DNS refresh behavior after a managed database failover.
  3. Zone redundancy was not enabled for an eligible database deployment.
  4. No eligible zone-redundant PostgreSQL standby was provisioned.

Explanation

Correct Answer

D:

The recorded behavior follows from: No eligible zone-redundant PostgreSQL standby was provisioned. The appropriate mitigation would be: Enable supported zone-redundant high availability with managed standby and compatible compute/region selection. Verify with: Inspect HA role, observe reconnect after a controlled test and validate data consistency.

Incorrect Answers

A:

The alternative weakness is: The messaging service tier/configuration does not meet zonal resilience requirements. Its associated failure is: A single-zone dependent messaging tier becomes unavailable during zonal maintenance. Neither explains the present observation: The server stays unavailable while a single-zone host is repaired. The direct cause here is: No eligible zone-redundant PostgreSQL standby was provisioned.

B:

This cause would explain a different symptom: A MySQL failover finishes but the API continues failing with stale database connections until every application instance is restarted. The mechanism for that event is: The client connection pool lacks robust reconnect and DNS refresh behavior after a managed database failover. Here the stated symptom is: The server stays unavailable while a single-zone host is repaired. Its cause is: No eligible zone-redundant PostgreSQL standby was provisioned.

C:

The proposed diagnosis fits another scenario: Zone redundancy was not enabled for an eligible database deployment. It would typically be reflected by: Single-zone database deployment becomes unavailable during a zonal outage. The current evidence instead supports: No eligible zone-redundant PostgreSQL standby was provisioned.

Question 648

The design change is: Enable supported zone-redundant high availability with managed standby and compatible compute/region selection. The original failure was: The server stays unavailable while a single-zone host is repaired. Which ongoing control best prevents recurrence of the same root cause?

  1. Monitor queue depths and backend availability after namespace scaling.
  2. Review the tier and region's zone support before database scaling or migration.
  3. Include client reconnection timing and error-budget recovery checks in planned MySQL high-availability drills.
  4. Monitor standby health and application retries after engine maintenance.

Explanation

Correct Answer

D:

The key follow-up control is: Monitor standby health and application retries after engine maintenance. It avoids recurrence of the scenario in which: The server stays unavailable while a single-zone host is repaired. It addresses: No eligible zone-redundant PostgreSQL standby was provisioned.

Incorrect Answers

A:

The proposed control focuses on: The messaging service tier/configuration does not meet zonal resilience requirements. For the design in the question, recurrence comes from: No eligible zone-redundant PostgreSQL standby was provisioned. A precise prevention step is: Monitor standby health and application retries after engine maintenance.

B:

That safeguard manages another risk: Zone redundancy was not enabled for an eligible database deployment. Its scenario is: Single-zone database deployment becomes unavailable during a zonal outage. The present recurring risk is: No eligible zone-redundant PostgreSQL standby was provisioned. The proper ongoing control is: Monitor standby health and application retries after engine maintenance.

C:

This is a reasonable safeguard for a different fault: A MySQL failover finishes but the API continues failing with stale database connections until every application instance is restarted. That different mechanism is: The client connection pool lacks robust reconnect and DNS refresh behavior after a managed database failover. The original incident here instead arises from: No eligible zone-redundant PostgreSQL standby was provisioned. The directly relevant safeguard is: Monitor standby health and application retries after engine maintenance.

Question 649

A design workshop has this requirement: Operations considers Azure Site Recovery alone sufficient for a five-nines availability target during ordinary VM host failures. Operators currently observe: Routine host outages cause long interruptions while region recovery replication remains healthy. Select the ONE design remedy that best addresses the root cause.

  1. Distribute supported AKS node pools across zones with multiple replicas and appropriate topology spread/anti-affinity.
  2. Enable supported zone-redundant high availability with managed standby and compatible compute/region selection.
  3. Deploy an availability set with suitable fault and update domains where availability zones aren't used.
  4. Deploy application-level high availability or availability-zone/VM redundancy for routine failures, with ASR reserved for DR.

Explanation

Correct Answer

D:

This option addresses the actual design defect: Disaster recovery orchestration does not substitute for continuous local high availability. The correction is: Deploy application-level high availability or availability-zone/VM redundancy for routine failures, with ASR reserved for DR. Confirm the outcome with: Simulate a host failure and verify service continues without manual recovery orchestration.

Incorrect Answers

A:

That design instead addresses another observed condition: Every application replica is scheduled onto nodes in one availability zone. Its technical cause is: Workload scheduling and node-pool placement lack zonal diversity. The current workload exhibits: Routine host outages cause long interruptions while region recovery replication remains healthy. Its targeted remedy is: Deploy application-level high availability or availability-zone/VM redundancy for routine failures, with ASR reserved for DR.

B:

This choice mitigates an alternative scenario, where: The server stays unavailable while a single-zone host is repaired. The underlying issue there is: No eligible zone-redundant PostgreSQL standby was provisioned. Here the root issue is: Disaster recovery orchestration does not substitute for continuous local high availability. Choose the corresponding action: Deploy application-level high availability or availability-zone/VM redundancy for routine failures, with ASR reserved for DR.

C:

The option belongs to a different failure mechanism: The VMs were not distributed across suitable update/fault domains. That situation exhibits: Both VMs restart for one planned host-maintenance event. For the stated case, the remedy is: Deploy application-level high availability or availability-zone/VM redundancy for routine failures, with ASR reserved for DR.

Question 650

The planned architecture is: Deploy application-level high availability or availability-zone/VM redundancy for routine failures, with ASR reserved for DR. Workload context: Operations considers Azure Site Recovery alone sufficient for a five-nines availability target during ordinary VM host failures. Which acceptance test demonstrates that the required behavior works?

  1. Inspect VM fault/update domain placement and test the expected maintenance/failure behavior.
  2. Simulate a host failure and verify service continues without manual recovery orchestration.
  3. Inspect HA role, observe reconnect after a controlled test and validate data consistency.
  4. Drain one zonal node pool and confirm healthy replicas remain available from other zones.

Explanation

Correct Answer

B:

The acceptance test is specific: Simulate a host failure and verify service continues without manual recovery orchestration. Its purpose is to establish that the proposed architecture works: Deploy application-level high availability or availability-zone/VM redundancy for routine failures, with ASR reserved for DR.

Incorrect Answers

A:

This check validates a different workload: Inspect VM fault/update domain placement and test the expected maintenance/failure behavior. Its associated design is: Deploy an availability set with suitable fault and update domains where availability zones aren't used. The required acceptance test here is: Simulate a host failure and verify service continues without manual recovery orchestration.

C:

The alternative test targets: Enable supported zone-redundant high availability with managed standby and compatible compute/region selection. The scenario's actual proposed remedy is: Deploy application-level high availability or availability-zone/VM redundancy for routine failures, with ASR reserved for DR. Verify that one by: Simulate a host failure and verify service continues without manual recovery orchestration.

D:

This check validates a different workload: Drain one zonal node pool and confirm healthy replicas remain available from other zones. Its associated design is: Distribute supported AKS node pools across zones with multiple replicas and appropriate topology spread/anti-affinity. The required acceptance test here is: Simulate a host failure and verify service continues without manual recovery orchestration.


Designing Microsoft Azure Infrastructure Solutions (AZ-305) Practice Tests

Purchase Individually

AZ-305 Premium File

Premium File
AZ-305 Premium File
382 Q&A
$76.99$69.99

AZ-305 Training Video Course

Training Course
AZ-305 Training Video Course
87 Lectures
$27.49$24.99

AZ-305 Study Guide

Study Guide
AZ-305 Study Guide
933 PDF Pages
$27.49$24.99

Site Search:

 

VISA, MasterCard, AmericanExpress, UnionPay

SPECIAL OFFER: GET 10% OFF

ExamCollection Premium

ExamCollection Premium Files

Pass your Exam with ExamCollection's PREMIUM files!

  • ExamCollection Certified Safe Files
  • Guaranteed to have ACTUAL Exam Questions
  • Up-to-Date Exam Study Material - Verified by Experts
  • Instant Downloads
Enter Your Email Address to Receive Your 10% Off Discount Code
A Confirmation Link will be sent to this email address to verify your login
We value your privacy. We will not rent or sell your email address

SPECIAL OFFER: GET 10% OFF

Use Discount Code:

MIN10OFF

A confirmation link was sent to your e-mail.
Please check your mailbox for a message from support@examcollection.com and follow the directions.

Next

Download Free Demo of VCE Exam Simulator

Experience Avanset VCE Exam Simulator for yourself.

Simply submit your e-mail address below to get started with our interactive software demo of your free trial.

Free Demo Limits: In the demo version you will be able to access only first 5 questions from exam.