Question 960
An OT risk owner is ready to close the follow-up after: A new packaging PLC can reach the local switch but not the designated supervisory subnet after its port was reconfigured as a trunk. Which evidence-and-prevention pairing best demonstrates both repair and recurrence control?
Explanation
Correct Answer
The measured result is: The PLC communicates only with the allowed supervisory endpoints on its intended VLAN. The preventive follow-up is: Include untagged versus tagged endpoint capabilities in switch-port templates. Together they establish a durable response to: The PLC sends untagged frames, while the changed native VLAN maps untagged traffic into the wrong zone.
Incorrect Answers
This evidence and prevention would close a different problem: A control historian's critical telemetry receives best-effort treatment over a congested aggregation link after a switch migration. The required current recovery evidence is: The PLC communicates only with the allowed supervisory endpoints on its intended VLAN.
That closure addresses a separate dependency: Two production cells intended to be separate receive the same VLAN ID across an uplink, and broadcast packets appear in both cells. The correct preventive control here is: Include untagged versus tagged endpoint capabilities in switch-port templates.
This evidence and prevention would close a different problem: A maintenance workstation swap causes the switch to shut down the approved engineering port even though the replacement is authorized. The required current recovery evidence is: The PLC communicates only with the allowed supervisory endpoints on its intended VLAN.