Question 230
An OT risk owner is ready to close the follow-up after: A historian sends 802.1Q-tagged packets for its OT telemetry VLAN but loses upstream communication after a new link is installed. Which evidence-and-prevention pairing best demonstrates both repair and recurrence control?
Explanation
Correct Answer
The measured result is: Historian tagged traffic traverses the link while unrelated VLANs remain excluded. The preventive follow-up is: Compare allowed-VLAN lists on both ends of each changed OT trunk. Together they establish a durable response to: The intermediate switch trunk does not allow the historian's tagged VLAN ID.
Incorrect Answers
The proposed closure would be relevant to another incident: Two production cells intended to be separate receive the same VLAN ID across an uplink, and broadcast packets appear in both cells. It does not demonstrate that the present cause is controlled: The intermediate switch trunk does not allow the historian's tagged VLAN ID.
That closure addresses a separate dependency: A passive OT sensor intermittently misses PLC identity flows during peak production on a shared mirror destination. The correct preventive control here is: Compare allowed-VLAN lists on both ends of each changed OT trunk.
The proposed closure would be relevant to another incident: An old industrial endpoint reports CRC errors and retransmissions after an unmanaged media converter is replaced. It does not demonstrate that the present cause is controlled: The intermediate switch trunk does not allow the historian's tagged VLAN ID.