Question 640
A job must wait for two parallel branches, but the developer encodes a time delay instead of explicit task dependencies. Which response best addresses the failure?
Explanation
Correct Answer
A fixed sleep period cannot guarantee parallel work has completed.
Incorrect Answers
Use supported repair-run behavior and make externally visible tasks idempotent: use supported repair-run behavior and make externally visible tasks idempotent: a failed downstream task does not automatically reverse successful earlier side effects; Model both predecessors as dependencies and execute the final task only after their required successful completion.
Declare the validation task as an explicit prerequisite for publishing in the job graph. This does not replace model both predecessors as dependencies and execute the final task only after their required successful completion.
Use suitable job compute and schedule the task hourly with measured startup and SLA headroom: use suitable job compute and schedule the task hourly with measured startup and SLA headroom: workload-specific job compute can avoid continuous idle capacity while meeting the refresh interval; Model both predecessors as dependencies and execute the final task only after their required successful completion.