Question 580
A developer deletes a bundle's workspace resources manually, but CI continues assuming they exist. What should the data engineer do FIRST?
Explanation
Correct Answer
Out-of-band changes cause drift between declared and actual resources. Reconcile resource state through supported deployment operations before release.
Incorrect Answers
The safe order is test, validate, approve and deploy; out-of-band changes cause drift between declared and actual resources.
Repeated deploys can compound unresolved configuration errors; out-of-band changes cause drift between declared and actual resources.
Operational readiness requires validating deployed behavior as well as resource creation; out-of-band changes cause drift between declared and actual resources.