Question 400
Two independent regional ingestions unnecessarily run in series and delay all downstream aggregation. Which action BEST addresses the stated requirement?
Explanation
Correct Answer
Parallel independent tasks can reduce critical-path duration. Run them as parallel DAG branches, then join at the dependent aggregation task.
Incorrect Answers
Logical parallelism is useful only when physical capacity supports it; parallel independent tasks can reduce critical-path duration.
Data completeness depends on all expected contributing tasks; parallel independent tasks can reduce critical-path duration.
Run overlap must not corrupt shared output state; parallel independent tasks can reduce critical-path duration.