Question 570
A project must weigh alternative actions with different probability-weighted costs. Which project-management action BEST addresses this situation?
Explanation
Correct Answer
Decision trees structure sequential choices under uncertainty. Here, a project must weigh alternative actions with different probability-weighted costs; the chosen action targets that failure. Verification: check each branch's expected consequence follows stated assumptions.
Incorrect Answers
This response addresses pareto chart, but the stated decision concerns decision tree. Pareto charts rank categories to focus improvement on major contributors.
This response addresses velocity chart, but the stated decision concerns decision tree. Velocity reflects historical completed work in a particular team context.
This response addresses fishbone diagram, but the stated decision concerns decision tree. Fishbone diagrams organize potential contributors to a defined problem.