Question 540
Operations asks if response-time variation is statistically outside expected limits. Which principle MOST directly explains how the project should be managed?
Explanation
Correct Answer
Control charts distinguish expected process variation from special causes. The situation involves operations asks if response-time variation is statistically outside expected limits, so this is the governing distinction.
Incorrect Answers
That principle concerns histogram rather than the problem of control chart. Histograms display frequencies across ranges of numeric values.
That principle concerns burnup chart rather than the problem of control chart. Burnup charts make scope growth visible alongside cumulative completion.
That principle concerns pareto chart rather than the problem of control chart. Pareto charts rank categories to focus improvement on major contributors.