Question 420
A completed outage migration repeats a prior project's avoidable mistakes. Which project-management action BEST addresses this situation?
Explanation
Correct Answer
Closure captures learning for future projects and operations. Here, a completed outage migration repeats a prior project's avoidable mistakes; the chosen action targets that failure. Verification: confirm future planning teams can retrieve actionable findings.
Incorrect Answers
This response addresses release resources, but the stated decision concerns lessons learned. Closure formally returns allocated resources to normal operations.
This response addresses deprovision access, but the stated decision concerns lessons learned. Project closeout includes revoking temporary access rights.
This response addresses contract closeout, but the stated decision concerns lessons learned. Contract closeout resolves remaining commercial obligations.