Every work package is estimated but some tasks have no available owner. Which project-management action BEST addresses this situation?
Explanation
Correct Answer
Resource plans must match competencies and actual availability. Here, every work package is estimated but some tasks have no available owner; the chosen action targets that failure. Verification: verify resource plan resolves overlaps and coverage gaps.
Incorrect Answers
This response addresses integrated project plan, but the stated decision concerns resource assignments. An integrated plan aligns related management areas under one delivery commitment.
This response addresses procurement needs, but the stated decision concerns resource assignments. Procurement planning accounts for external acquisition constraints.
This response addresses budget estimate, but the stated decision concerns resource assignments. A defensible budget includes all material lifecycle project costs.