Question 20
Developers need a short regular cadence for backlog planning and working increments. Which caution is MOST directly relevant to the project manager's decision?
Explanation
Correct Answer
A sprint is not a guarantee that every requested feature will be completed. The underlying reason is that scrum delivers in short cycles and adapts the product backlog based on feedback.
Incorrect Answers
This is a caution about kanban workflow, not the immediate risk in scrum iteration. Kanban emphasizes continuous flow, visible work and constrained work in progress.
This is a caution about portfolio prioritization, not the immediate risk in scrum iteration. A portfolio prioritizes projects and programs to meet organizational strategy.
This is a caution about unique deliverable, not the immediate risk in scrum iteration. A project is temporary and creates a unique product, service or result.