Question 20
A technician proposes enabling a new firewall rule for a production server and says no review is needed because the change will take ten seconds. What response is most defensible?
Explanation
Correct Answer
Even a short technical action can expose critical services, so risk-based change control applies.
Incorrect Answers
Invoke the documented emergency-change process with required expedited authorization and post-implementation review: urgency may change the approval path but does not remove accountability or evidence requirements.
Defer the normal change until the permitted window or obtain a justified formally approved exception: a change freeze protects business-critical operations from avoidable risk during sensitive periods; Submit the change with business reason, impact, risk, approvals and a tested rollback plan.
Use the organization's standard-change workflow if it is already approved and within its defined scope: a preauthorized standard change can reduce unnecessary review while preserving a documented and repeatable method.