Here is a sample question, from hotcerts and certkiller.
QUESTION 1:
You work for Certkiller .com and are responsible for the Release Management role on a project. The project is currently in the Deploying Phase.
You are deploying a corporate application to several regional offices in cities across the country.Your team deploying the application in each office consecutively.To minimize deployment costs, the travel schedule is
aggressive, and the time spent at each office site is limited.
Your customer reports that the solution at each site is unstable and that user feedback indicates that users is not satisfied. The central help desk is receiving a large number of support requests. The Deployment team cannot respond, because they are currently involved with another site deployment. Reports show that users access the system. User training has occurred.
What is the most likely cause of the problem?
A.The Core Technology Deployed Milestone was not completed before the site deployments began.
B.The Site Installation Complete Milestone was not achieved during the site installation.
C.The Site Training Complete Milestone was not achieved during the site deployment.
D.The Site Deployment Complete Milestone was not achieved during the site deployment.
Answer: D